Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
Ceiling Rough Electrical | 7/3/2025 | M.Green | | | View Scheduled Inspection | 861932 |
Ceiling Rough Electrical | 7/3/2025 | M.Green | | | View Scheduled Inspection | 860843 |
Ceiling Rough Electrical | 6/25/2025 | M.Green | 6/26/2025 1:55:53 PM | Partial | Completed | 860250 |
Ceiling Rough Electrical | 6/25/2025 | M.Green | 6/26/2025 1:48:34 PM | Partial | Completed | 860470 |
Ceiling Rough Electrical | 6/23/2025 | M.Green | 6/24/2025 7:17:15 AM | Correction | Completed | 851793 |
Ceiling Rough Electrical | 4/25/2025 | E.Widman | 4/25/2025 3:36:13 PM | Partial | Completed | 851224 |
Ceiling Rough Electrical | 4/23/2025 | E.Widman | 4/23/2025 3:08:43 PM | Partial | Completed | 848777 |
Ceiling Rough Electrical | 4/7/2025 | N.Holland | 4/7/2025 3:15:50 PM | Partial | Completed | 848459 |
Ceiling Rough Electrical | 4/4/2025 | E.Widman | 4/4/2025 2:46:14 PM | Partial | Completed | 847890 |
Ceiling Rough Electrical | 4/3/2025 | E.Widman | 4/3/2025 4:24:42 PM | Correction | Completed | 844558 |
Ceiling Rough Electrical | 3/6/2025 | M.Green | 3/6/2025 2:03:57 PM | Partial | Completed | 835948 |
Ceiling Rough Electrical | 12/13/2024 | M.Green | 12/13/2024 3:26:19 PM | Correction | Completed | 835484 |
Ceiling Rough Electrical | 12/12/2024 | M.Green | 12/13/2024 9:01:12 AM | Correction | Completed | 805606 |
Concrete Encased Electrode | | | | | Schedule Inspection | 832390 |
Concrete Encased Electrode | 11/12/2024 | M.Green | 11/13/2024 8:38:51 AM | Partial | Completed | 825676 |
Concrete Encased Electrode | 9/26/2024 | M.Green | 9/26/2024 3:15:53 PM | Cancel | Completed | 805610 |
Electrical Rough | | | | | Schedule Inspection | 856359 |
Electrical Rough | | | | | Schedule Inspection | 851626 |
Electrical Rough | 5/28/2025 | M.Green | 5/29/2025 7:24:27 AM | Partial | Completed | 856081 |
Electrical Rough | 4/24/2025 | E.Widman | 4/24/2025 3:32:25 PM | Correction | Completed | 848188 |
Electrical Rough | 4/2/2025 | E.Widman | 4/2/2025 3:20:25 PM | Partial | Completed | 846214 |
Electrical Rough | 3/19/2025 | M.Green | 3/20/2025 7:32:44 AM | Partial | Completed | 845539 |
Electrical Rough | 3/18/2025 | M.Green | 3/18/2025 1:51:04 PM | Cancel | Completed | 845538 |
Electrical Rough | 3/17/2025 | M.Green | 3/17/2025 11:40:58 AM | Correction | Completed | 845537 |
Electrical Rough | 3/14/2025 | M.Green | 3/17/2025 11:34:29 AM | Partial | Completed | 843080 |
Electrical Rough | 2/24/2025 | M.Green | 2/25/2025 9:58:11 AM | Partial | Completed | 842845 |
Electrical Rough | 2/21/2025 | M.Green | 2/21/2025 2:36:11 PM | Partial | Completed | 836406 |
Electrical Rough | 12/23/2024 | M.Green | 12/23/2024 3:11:00 PM | Partial | Completed | 835489 |
Electrical Rough | 12/16/2024 | M.Green | 12/20/2024 7:58:23 AM | Cancel | Completed | 834783 |
Electrical Rough | 12/19/2024 | M.Green | 12/19/2024 2:18:05 PM | Partial | Completed | 835488 |
Electrical Rough | 12/18/2024 | M.Green | 12/18/2024 3:32:51 PM | Correction | Completed | 836272 |
Electrical Rough | 12/17/2024 | M.Green | 12/18/2024 10:10:24 AM | Partial | Completed | 835487 |
Electrical Rough | 12/4/2024 | M.Green | 12/4/2024 3:18:57 PM | Partial | Completed | 833704 |
Electrical Rough | 11/21/2024 | E.Widman | 11/21/2024 2:17:04 PM | Partial | Completed | 832391 |
Electrical Rough | 11/12/2024 | M.Green | 11/13/2024 8:48:06 AM | Partial | Completed | 831802 |
Electrical Rough | 11/8/2024 | M.Green | 11/12/2024 7:19:14 AM | Partial | Completed | 827563 |
Electrical Rough | 10/9/2024 | M.Green | 10/10/2024 9:12:45 AM | Partial | Completed | 825936 |
Electrical Rough | 10/8/2024 | M.Green | 10/9/2024 7:15:16 AM | Partial | Completed | 825937 |
Electrical Rough | 10/7/2024 | M.Green | 10/7/2024 3:21:33 PM | Partial | Completed | 825935 |
Electrical Rough | 10/4/2024 | M.Green | 10/7/2024 7:36:59 AM | Partial | Completed | 825934 |
Electrical Rough | 10/2/2024 | M.Green | 10/4/2024 7:21:11 AM | Partial | Completed | 825932 |
Electrical Rough | 10/3/2024 | M.Green | 10/3/2024 7:48:41 AM | Partial | Completed | 825933 |
Electrical Rough | 10/1/2024 | M.Green | 10/2/2024 7:08:52 AM | Partial | Completed | 825931 |
Electrical Rough | 9/30/2024 | M.Green | 10/1/2024 8:56:05 AM | Correction | Completed | 822796 |
Electrical Rough | 9/10/2024 | V.Fosberg | 9/10/2024 2:21:02 PM | Cancel | Completed | 821437 |
Electrical Rough | 9/9/2024 | O.Burbridge | 9/9/2024 3:17:51 PM | Correction | Completed | 821436 |
Electrical Rough | 9/3/2024 | M.Green | 9/3/2024 8:20:52 AM | Cancel | Completed | 821183 |
Electrical Rough | 8/30/2024 | M.Green | 9/3/2024 7:10:07 AM | Partial | Completed | 819040 |
Electrical Rough | 8/15/2024 | M.Green | 8/16/2024 7:11:44 AM | Partial | Completed | 817396 |
Electrical Rough | 8/6/2024 | M.Green | 8/7/2024 9:42:37 AM | Partial | Completed | 816882 |
Electrical Rough | 8/5/2024 | M.Green | 8/5/2024 2:56:54 PM | Partial | Completed | 816653 |
Electrical Rough | 8/2/2024 | M.Green | 8/2/2024 2:59:17 PM | Partial | Completed | 811860 |
Electrical Rough | 7/1/2024 | V.Fosberg | 7/1/2024 11:06:26 AM | Cancel | Completed | 811727 |
Electrical Rough | 6/28/2024 | E.Widman | 6/28/2024 3:16:07 PM | Progress | Completed | 811130 |
Electrical Rough | 6/27/2024 | E.Widman | 6/27/2024 3:11:32 PM | Correction | Completed | 811129 |
Electrical Rough | 6/26/2024 | M.Green | 6/27/2024 7:37:48 AM | Partial | Completed | 810868 |
Electrical Rough | 6/21/2024 | M.Green | 6/24/2024 3:29:04 PM | Partial | Completed | 808846 |
Electrical Rough | 6/11/2024 | M.Green | 6/12/2024 7:23:58 AM | Correction | Completed | 806160 |
Electrical Rough | 5/24/2024 | E.Widman | 5/24/2024 1:45:49 PM | Partial | Completed | 805612 |
Electrical Rough | 5/23/2024 | E.Widman | 5/23/2024 3:37:28 PM | Partial | Completed | 804179 |
Electrical Rough | 5/10/2024 | M.Green | 5/13/2024 9:15:03 AM | Correction | Completed | 803958 |
Electrical Temporary | | | | | Schedule Inspection | 734694 |
Electrical Temporary | 9/28/2022 | E.Widman | 9/28/2022 1:39:09 PM | Partial | Completed | 734515 |
Final Electrical | | | | | Schedule Inspection | 805607 |
Final Zoning | | | | | Schedule Inspection | 805613 |
Pools Spa Rough | 7/3/2025 | M.Green | | | View Scheduled Inspection | 861923 |
Pools Spa Rough | | | | | Schedule Inspection | 861392 |
Pools Spa Rough | | | | | Schedule Inspection | 841477 |
Pools Spa Rough | | | | | Schedule Inspection | 814121 |
Pools Spa Rough | 6/30/2025 | M.Green | 6/30/2025 3:08:00 PM | Cancel | Completed | 861161 |
Pools Spa Rough | 2/7/2025 | M.Green | 2/10/2025 7:50:14 AM | Partial | Completed | 841061 |
Pools Spa Rough | 7/16/2024 | M.Green | 7/17/2024 7:27:17 AM | Partial | Completed | 813836 |
Service | | | | | Schedule Inspection | 848971 |
Service | 4/9/2025 | E.Widman | 4/10/2025 3:30:18 PM | Correction | Completed | 805609 |
Service | 4/8/2025 | E.Widman | 4/8/2025 3:07:36 PM | Correction | Completed | 848621 |
Temp Electric | | | | | Schedule Inspection | 734518 |
Temp Electric | 9/27/2022 | O.Burbridge | 9/27/2022 2:34:37 PM | Correction | Completed | 651736 |
Undergound Electrical | | | | | Schedule Inspection | 805611 |
Undergound Electrical | 11/11/2024 | M.Green | 11/13/2024 8:42:43 AM | Partial | Completed | 728527 |
Undergound Electrical | 8/17/2022 | N.Holland | 8/17/2022 11:41:25 AM | Partial | Completed | 724490 |
Undergound Electrical | 7/25/2022 | M.Green | 7/25/2022 9:22:00 AM | Partial | Completed | 724272 |
Undergound Electrical | 7/21/2022 | O.Burbridge | 7/22/2022 9:30:31 AM | Partial | Completed | 721808 |
Undergound Electrical | 7/7/2022 | M.Green | 7/7/2022 2:50:10 PM | Partial | Completed | 685597 |
Undergound Electrical | 9/29/2021 | M.Green | 9/29/2021 12:28:56 PM | Partial | Completed | 680694 |
Wall Rough Electrical | | | | | Schedule Inspection | 805608 |