Inspection #: 903878
Inspection Type: Final Electrical
Inspector: M.Green
Result: Partial
Comment: New general contractor walk-through to determine outstanding corrections. Previous list of corrections was contained in inspection #903255 dated 5/29/2026. Only some of those corrections carried forward to this inspection. Items corrected: *GFCI protection for pool lighting. *GFCI protection for TV receptacle. *EMT for pool pump room lighting replaced with PVC. Remaining corrections below. CURRENT CONDITIONAL ELECTRICAL FINAL EXTENDED UNTIL 8/31/2026. SEE CORRECTIONS BELOW TO EXTEND CONDITIONAL ELECTRICAL FINAL TO GAZEBO and pool.

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
6/30/2026TransferCorrect Below* To extend conditional electrical final to gazebo.Conditional electrical finals can only by issued for completed phased areas. The gazebo is part of Phase 4. Phase 4 is the gazebo and pool. Disconnect / lock-out the waterfall low voltage light until a permanent resolution of issues can be achieved.
6/30/2026TransferCorrect Below* Rooftop.2 out of 3 units not listed.
6/30/2026TransferCorrect Below* 3RD floor heat trace breakers. Breaker locking devices installed do not meet the requirements of 110.25. NOTE: 426.50(A) requires that disconnecting means is capable of being locked in the open position.
6/30/2026TransferCorrect Below* Pool area low voltage "waterfall" light.Low voltage lighting within 5ft of pool is required to conform to 680.22(B)(6). Specific low voltage power source requirements are at 680.23(A)(2). UPDATE: RECEIVED "BRILLIANT WONDERS" POOL WATERFALL LIGHT PRODUCT INFORMATION. POWER SUPPLY INSTALLED DOES NOT CONFORM TO THE NEC SECTION ABOVE. ETL LISTING REP FOR THE COMPANY NEEDS TO CONTACT INSPECTOR.
5/29/2026TransferCorrect Below* All units with dishwashers and disposals.Field installation has both appliances on the same circuit. Verify that engineer has submitted change order to MOA Plan Review.
5/29/2026TransferCorrect Below* 50A elevator circuits.1-line drawing shows (4) 50A elevator circuits supplied directly from MDP. Installation varies from 1-line drawing. Requires change order submitted to MOA Plan Review to show: 1. Coordination study between 200A feeder OCPD and 50A elevator circuit OCPDs. 2. 1-line changed to show 50A elevator circuits supplied from 200A elevator panels as installed. 3. Recalculated available fault current.
5/29/2026TransferCorrect Below* Available fault current table on drawings.Various panels show less than 10K available fault current. Table shows 22K equipment rating. Change table to allow 10K breakers and submit to MOA Plan Review for approval.