Muni.org > Departments > Development Services> Permit Information & Inspection Request
Click Here To View Another Inspection


Inspection #: 886116
Inspection Type: Final Electrical
Inspector: M.Green
Result: Partial
Comment: Phase 1 and Phase 2 conditional electrical final approved until 2/25/2025. Correct the following and request reinspection. Phase 3 (ADA rooms) and Phase 4 (Pool and associated spaces / rooms and Gazebo) are not included in this inspection. Requested by: Coleman Barney, Mike McManus 9079781471 907-987-9353 cb@g2const.com

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
12/22/2025TransferCorrect Below* All units with dishwashers and disposals.Contractor has put both appliances on one circuit. DW and disp. total draw is less than 16A so no NEC violation. Engineer needs to submit change order to MOA Plan Review to approve / acknowledge.
12/22/2025TransferCorrect Below* 50A rooftop AC units.Do not have listing labels.
12/22/2025TransferCorrect Below* Parking lot pole lights.Require a ground wire connection at the hand hole.
12/22/2025TransferCorrect Below* 2nd floor electrical room.Several heat trace GFCI breakers require breaker locks.