Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
Bond Beam | | | | | Schedule Inspection | 519749 |
Bond Beam | 5/12/2025 | P.Calhoun | 5/12/2025 2:53:55 PM | Approved | Completed | 853852 |
Bond Beam | 5/7/2025 | P.Calhoun | 5/7/2025 3:02:45 PM | Approved | Completed | 853359 |
Bond Beam | 5/6/2025 | P.Calhoun | 5/7/2025 9:55:52 AM | Approved | Completed | 852974 |
Ceiling / Act | | | | | Schedule Inspection | 519748 |
Final Structural | | | | | Schedule Inspection | 519752 |
Final Zoning | | | | | Schedule Inspection | 519753 |
FireStopping | | | | | Schedule Inspection | 551163 |
Footing | 6/12/2025 | P.Calhoun | 6/12/2025 1:59:49 PM | Approved | Completed | 858132 |
Footing | 5/30/2025 | P.Calhoun | 5/30/2025 4:43:30 PM | Approved | Completed | 856701 |
Footing | 5/12/2025 | P.Calhoun | 5/12/2025 2:51:42 PM | Approved | Completed | 853642 |
Footing | 4/3/2025 | P.Calhoun | 4/3/2025 12:24:45 PM | Approved | Completed | 848114 |
Footing | 1/6/2025 | P.Calhoun | 1/6/2025 2:42:28 PM | Approved | Completed | 837385 |
Footing | 1/2/2025 | P.Calhoun | 1/2/2025 12:46:35 PM | Correction | Completed | 837244 |
Footing | 11/8/2024 | P.Calhoun | 11/8/2024 9:33:43 AM | Approved | Completed | 831825 |
Footing | 11/1/2024 | B.Gilgus | 11/1/2024 9:29:29 AM | Approved | Completed | 543372 |
Foundation | 1/21/2025 | P.Calhoun | | Cancel | Completed | 838903 |
Foundation | 5/23/2025 | P.Calhoun | 5/27/2025 7:24:57 AM | Approved | Completed | 855559 |
Foundation | 5/15/2025 | P.Calhoun | 5/16/2025 7:12:03 AM | Approved | Completed | 854506 |
Foundation | 5/2/2025 | P.Calhoun | 5/2/2025 12:41:12 PM | Approved | Completed | 852232 |
Foundation | 4/26/2025 | P.Calhoun | 4/28/2025 10:04:27 AM | Approved | Completed | 851747 |
Foundation | 4/24/2025 | P.Calhoun | 4/28/2025 7:06:16 AM | Approved | Completed | 851247 |
Foundation | 4/10/2025 | B.Gilgus | 4/10/2025 12:57:48 PM | Approved | Completed | 849165 |
Foundation | 2/12/2025 | P.Calhoun | 2/12/2025 10:10:01 AM | Approved | Completed | 841296 |
Foundation | 1/22/2025 | P.Calhoun | 1/22/2025 1:26:59 PM | Approved | Completed | 838940 |
Foundation | 12/6/2024 | P.Calhoun | 12/6/2024 11:27:46 AM | Approved | Completed | 834646 |
Foundation | 12/3/2024 | P.Calhoun | 12/3/2024 1:51:00 PM | Approved | Completed | 834037 |
Foundation | 11/25/2024 | P.Calhoun | 11/25/2024 2:41:40 PM | Correction | Completed | 833458 |
Foundation | 11/15/2024 | P.Calhoun | 11/15/2024 1:35:44 PM | Approved | Completed | 826451 |
Foundation | 10/1/2024 | P.Calhoun | 10/1/2024 2:36:44 PM | Partial | Completed | 826210 |
Framing | | | | | Schedule Inspection | 862155 |
Framing | 7/3/2025 | P.Calhoun | 7/3/2025 2:38:38 PM | Correction | Completed | 860080 |
Framing | 6/23/2025 | P.Calhoun | 6/23/2025 1:26:41 PM | Cancel | Completed | 859648 |
Framing / Ext. | 6/3/2025 | P.Calhoun | 6/5/2025 7:24:33 AM | Approved | Completed | 856892 |
Framing / Ext. | 6/2/2025 | P.Calhoun | 6/2/2025 11:49:13 AM | Correction | Completed | 855540 |
Framing / Ext. | 5/22/2025 | P.Calhoun | 5/22/2025 9:59:31 AM | Partial | Completed | 855469 |
Insulation / Vapor Barrier | 1/29/2025 | P.Calhoun | 1/29/2025 8:28:39 AM | Approved | Completed | 840035 |
Insulation / Vapor Barrier | 1/28/2025 | P.Calhoun | 1/28/2025 2:52:25 PM | Correction | Completed | 839692 |
Insulation / Vapor Barrier | 12/3/2024 | P.Calhoun | 12/3/2024 10:50:46 AM | Approved | Completed | 834505 |
Insulation / Vapor Barrier | 12/2/2024 | P.Calhoun | 12/2/2024 1:10:04 PM | Correction | Completed | 834400 |
Other Structural | | | | | Schedule Inspection | 550745 |
Other Structural | | | | | Schedule Inspection | 542348 |
Pollution Discharge System | | | | | Schedule Inspection | 519776 |
Pre Zoning | | | | | Schedule Inspection | 519760 |
Pre-Construction Meeting | 5/7/2025 | P.Calhoun | 5/7/2025 9:23:23 AM | NA | Completed | 853209 |
Pre-Construction Meeting | 6/11/2018 | D.Hickel | 6/11/2018 9:51:12 AM | Approved | Completed | 520403 |
Private Development Site Civil | | P.Ronning | | | Schedule Inspection | 519769 |
S.A.Fireproofing | 6/23/2025 | P.Calhoun | 6/23/2025 3:21:01 PM | Approved | Completed | 519775 |
Shaftwall | | | | | Schedule Inspection | 519764 |
Shearwall / Exterior | | | | | Schedule Inspection | 548521 |
Steel Bolting / Welding | 6/5/2025 | P.Calhoun | 6/5/2025 1:24:51 PM | Approved | Completed | 857280 |
StormWater Inspection-Annual | 5/15/2020 | C.Weed | 9/27/2021 11:47:00 AM | Approved | Completed | 588126 |
StormWater Inspection-Annual | 10/7/2019 | C.Weed | 10/15/2019 2:43:00 PM | Progress | Completed | 576088 |
StormWater Inspection-Annual | 8/5/2019 | C.Weed | 8/5/2019 9:16:00 AM | Progress | Completed | 570451 |
StormWater Inspection-Annual | 6/24/2019 | C.Weed | 6/25/2019 11:01:00 AM | Progress | Completed | 565035 |
StormWater Inspection-Annual | 5/8/2019 | C.Weed | 5/21/2019 2:18:00 PM | Progress | Completed | 545146 |
StormWater Inspection-Monthy | 11/7/2024 | C.Weed | | | View Scheduled Inspection | 827145 |
StormWater Inspection-Monthy | 10/2/2024 | C.Weed | 10/2/2024 9:03:00 AM | Progress | Completed | 827144 |
StormWater Inspection-Monthy | | C.Weed | 9/27/2024 8:57:00 AM | Correction | Completed | 824108 |
Temp Electric | | | | | Schedule Inspection | 519771 |