78,062 sq ft (4) story mixed occupancy hotel OK TO ISSUE GRADING/EXCAVATION WITHOUT FEES PAID PER GRETCHEN 9/1/2017 PLAN REVIEW FEES PAID IN FULL, X17-1099 PAID IN FULL 6/6/18 ***10/9/18 OKAY FOR GENERAL TO P/U FOR JM MECH... SLO
***OK FOR F&F AND CORE/SHELL ONLY! - CHANGE ORDER REQUIRED FOR UPDATED CIVIL PLANS TO INLCUDE SHARED ACCESS (REF PERMIT #C21-1153) PRIOR TO ISSUING FULL PERMIT - RDO / G.SOULE 03/18/24***
*** ORIGINAL FEES WERE PAID BY CHECK WRITTEN BY PROPERTY OWNERS (ANCHORAGE MC HOLDING LLC). WRITTEN LETTER BY OWNER REQUIRED FOR EACH CONTRACTOR TRASNFER (ALL DISCIPLINES AS NECESSARY) - RED 6/26/24
MOA & MC HOLDING LLC AGREEMENT OF REINSPECTION FEES DUE (169 INSPECTIONS @$175/EA LOADED IN INFOR 7/2/24) TO PROCEED WITH PROJECT (EMAIL ATTACHED FOR RECORDS ALONG WITH TRANSFER OF CONTRACTORS TO JANSEN AS GENERAL AND SAMSON FOR ELECTRICAL)- RED 7/2/24
FULL PERMIT ISSUED - 9/3/24 - RED
Reviewed by: Bergstrom, Leigh W. Permit #: C15-1806
Phone: 343-8326 Date: 4/25/2016
Fax: 249-7615
Email: BergstromLW@muni.org
Permit Manager: Tony Barganier
Phone: 343-8339
Email: BarganierTA@muni.org
Project: COURTYARD BY MARRIOTT
Review Number: 370889
1) STATUS: 9-01-15 Comments to be addressed. 2-24-2016 APPROVED FOR FOOTING AND FOUNDATION ONLY. COMMENTS TO BE ADDRESSED. 4-07-2016 COMMENTS TO BE ADDRESSED. 4-25-2016 APPROVED.
2) The following comments based on the 2009 International Building, Mechanical and Fuel Gas Codes must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the IBC, IMC, IFGC or any federal, state or local regulations. RESOLVED 2-24-2016.
3) Provide structural, seismic and wind load calculations as applicable, plus fastening details for BP-1, MAU-1 & 2, KMU-1 & 2, DF-1, Type I Kitchen Hood (#71), Type II Dishwasher Hood (#36) and DHU-1 to include engineers stamp and signature, for structural review on a deferred submittal basis. RESOLVED 2-24-2016.
4) M2.1 thru M2.4 The 50 CFM supply duct to each sleeping unit requires a fire damper where the duct penetrates the 1-Hour wall at the corrodor. (IMC 607.5.3) RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
5) M2.2 Clarify Key Note #7 at louver L-5. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
6) M2.2 thru M2.4 The 50 CFM supply duct to King Mod 1 between column lines 15 and 16 may not pass through a rated shaft without fire/smoke dampers at each penetration. (IMC 607.5.5) RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
7) M2.6 Clarify Key Note #20 at 2 ea RG-2 along column line #9. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
8) M2.6 Clarify Key Note #19 adjacent to column line #15. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
9) M2.6 The grease duct requires its own separate rated shaft up through the roof per IMC 506.3.10. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
10) M2.6 A grease duct serving a Type I hood that penetrates a ceiling, shall be enclosed from the point of penetration to the outlet terminal. The duct enclosure shall not contain other ducts, piping or wiring systems. (IMC 506.3.10) RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
11) M2.6 The two outside air ducts and the 12" dishwasher exhaust duct require fire/smoke dampers where they penetrate the rated shaft above the kitchen. (IMC 607.5.5) RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
12) M2.6 The FSD for the air transfer duct at the Engineering Maintenance Office is required to be located at the penetration of the fire partition/corridor wall. (IMC 607.5.3) RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
13) M2.6 The Type I hood and grease duct require 18" clearance from combustible construction per IMC 507.9 and 506.3.6. Provide details. 2-12-2016 UNRESOLVED. ARCHITECTURAL SHEET A101a INDICATES THAT THE WALL BEHIND THE HOOD IS TO BE TYPE E.2 CONSTRUCTION WHICH HAS WOOD STUDS AND DOES NOT MEET THE REQUIREMENTS OF IMC 507.9. RESOLVED PER RE-SUBMITTAL RECEIVED 3-15-2016.
14) M2.6 Key Note #8 indicates the Pool and Spa Heaters are expected to be 300 MBH each while schematic 7/P4.0 indicates 400 MBH each. Please clarify. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
15) M3.1 Clarify the secondary drainage system for the PTHP-1 units per IMC 307.2.3. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
16) M3.1 Provide a schedule for the Grease Hood #71 and Dishwasher Hood #36. 2-24-2016 UNRESOLVED. REQUESTED INFORMATION IS REQUIRED IN ORDER TO COMPLETE THE MECHANICAL REVIEW. 4-07-2017 UNRESOLVED. PROVIDE THE SCHEDULE WITHIN THE MECHANICAL PLAN SET PROVIDING MODEL NUMBERS WITH SPECIFIC INFORMATION PERTAINING TO THIS PROJECT. RESOLVED PER RE-SUBMITTAL RECEIVED 4-22-2016.
17) 3/M4.1 The supply and return air ducts to the vertical downflow fancoil units pass through rated floor/ceiling assemblies and require fire dampers per IMC 607.6.1. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
18) Provide details for the installation of the pool and spa heaters to include engineers stamp and signature, on a deferred submittal basis. RESOLVED PER RE-SUBMITTAL RECEIVED 2-05-2016.
19) 2-24-2016 New M2.1 It appears that intake louver #L2 will be located less than 10 feet away from the gas pressure regulator vent adjacent to the gas meter. (IMC 401.4.2) 4-07-2016 UNRESOLVED. THE VENT OUTLET FROM THE PRESSURE REDUCING VALVE WILL BE ON THE INCOMING (STREET) SIDE OF THE GAS METER WHICH WOULD HORIZONTALLY PLACE IT AT THE CORNER OF THE BUILDING, ONLY ABOUT 3-1/2 FEET FROM THE NEW LOCATION OF LOUVER #L2. THE TRAVEL DISTANCE BETWEEN THE TWO ITEMS NEEDS TO BE AT LEAST 10 FEET. RESOLVED PER RE-SUBMITTAL RECEIVED 4-22-2016.
20) When the above comments have been addressed please update the plans at the MOA Plans Review Office with three sets of revised mechanical pages to include clouded changes, engineers stamp and signature. RE-SUBMITTALS ARE TO BE DIRECTED TO THE ATTENTION OF THE PERMIT MANAGER WITH A LETTER OF RESPONSE ADDRESSING EACH COMMENT.
RESOLVED 4-25-2016.