| Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
| Ceiling / Act | 3/27/2018 | D.Hickel | 3/27/2018 10:43:16 AM | Approved | Completed | 509737 |
| Ceiling / Act | 3/13/2018 | P.Calhoun | 3/13/2018 12:36:30 PM | Correction | Completed | 508283 |
| Ceiling / Act | 2/15/2018 | H.Kahlstrom | 2/15/2018 10:46:43 AM | Approved | Completed | 505820 |
| Ceiling / Act | 2/1/2018 | B.Gilgus | 2/1/2018 9:43:20 AM | Approved | Completed | 463851 |
| Ceiling / Act | 8/11/2017 | D.Hickel | 8/11/2017 1:02:06 PM | Approved | Completed | 465653 |
| Ceiling / Act | 7/24/2017 | D.Hickel | 7/24/2017 1:44:03 PM | Partial | Completed | 463836 |
| Final Fire Inspection | 5/9/2018 | M.Warren | 5/9/2018 3:34:34 PM | Approved | Completed | 514173 |
| Final Fire Inspection | 4/25/2018 | M.Warren | 4/27/2018 7:54:59 AM | Correction | Completed | 513737 |
| Final Fire Inspection | 8/15/2017 | M.Warren | 8/15/2017 3:44:50 PM | CondAppr | Completed | 463858 |
| Final Structural | 7/20/2018 | H.Kahlstrom | 7/20/2018 12:09:55 PM | Approved | Completed | 515883 |
| Final Structural | 5/9/2018 | D.Hickel | 5/9/2018 10:45:49 AM | Partial | Completed | 515882 |
| Final Structural | 5/4/2018 | H.Kahlstrom | 5/4/2018 1:25:10 PM | Correction | Completed | 469226 |
| Final Structural | 8/15/2017 | D.Hickel | 8/15/2017 1:25:14 PM | Partial | Completed | 463840 |
| Final Zoning | 6/13/2018 | C.Weaver | 6/13/2018 3:04:00 PM | Approved | Completed | 463841 |
| Footing | 8/25/2017 | D.Hickel | 8/28/2017 7:09:16 AM | Approved | Completed | 466213 |
| Footing | 8/18/2017 | D.Hickel | 8/18/2017 10:43:26 AM | Approved | Completed | 463842 |
| Footing | 7/26/2017 | D.Hickel | 7/27/2017 2:55:19 PM | Partial | Completed | 463848 |
| Foundation | 8/23/2017 | D.Hickel | 8/23/2017 3:13:42 PM | Approved | Completed | 463843 |
| Foundation | 8/10/2017 | D.Hickel | 8/10/2017 2:50:13 PM | Approved | Completed | 462367 |
| Framing | 9/26/2017 | D.Hickel | 9/26/2017 10:28:34 AM | Approved | Completed | 463845 |
| Framing / Ext. | 11/9/2017 | D.Hickel | 11/9/2017 3:10:29 PM | Approved | Completed | 462693 |
| Framing / Int. | 12/4/2017 | D.Hickel | 12/4/2017 2:12:46 PM | Approved | Completed | 495122 |
| Framing / Int. | 11/13/2017 | D.Hickel | 11/14/2017 9:27:53 AM | Correction | Completed | 494467 |
| Framing / Int. | 7/5/2017 | D.Blackburn | 7/5/2017 12:40:00 PM | Partial | Completed | 462366 |
| Insulation / Vapor Barrier | 10/10/2017 | D.Blackburn | 10/10/2017 12:03:01 PM | Approved | Completed | 463847 |
| Metal Pan Decking | 10/18/2017 | D.Hickel | 10/18/2017 2:02:50 PM | Approved | Completed | 463849 |
| Pre-Construction Meeting | 7/24/2017 | D.Blackburn | 7/24/2017 9:59:45 AM | NA | Completed | 465576 |
| Shaftwall | 1/4/2018 | D.Hickel | 1/4/2018 11:17:06 AM | Approved | Completed | 463853 |
| StormWater Inspection-Annual | | R.Deley | 8/13/2018 4:34:49 PM | Approved | Completed | 530218 |
| StormWater Inspection-Annual | 8/22/2018 | R.Deley | 8/23/2017 8:44:43 AM | Progress | Completed | 459481 |