| Date | Status | Code | Description | Ref | Location | Comments |
| 5/4/2018 | Corrected | FNLSG | Final Structural Other | Please correct the following: | | Provide final S.I. report summary/ closure letter. |
| 5/4/2018 | Transfer | FNLSG | Final Structural Other | Please correct the following: | Sorage room 18 | Provide door hardware. |
| 5/4/2018 | Transfer | FNLSG | Final Structural Other | Please correct the following: | Doors at new wing | Provide signage at all doors |
| 5/4/2018 | Transfer | FNLSB | NC Handrails | Handrails to be 34" - 38" above the stairs measured at the nose of the stair in a plumb line | Ramp exiting library | Complete handrail and return at ramp |