Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
Fire Sprinkler Bracing Final | 12/10/2021 | D.Meneses | 12/10/2021 10:38:00 AM | Partial | Completed | 695090 |
Fire Sprinkler Final | 5/12/2022 | D.Meneses | 5/12/2022 8:44:00 AM | Approved | Completed | 710098 |
Fire Sprinkler Final | 4/19/2022 | D.Meneses | 4/19/2022 9:52:00 AM | Partial | Completed | 704315 |
Fire Sprinkler Final | 4/14/2022 | D.Meneses | 4/14/2022 2:53:00 PM | Correction | Completed | 660271 |
Fire Sprinkler Final | 3/7/2022 | D.Meneses | 3/7/2022 2:41:00 PM | Correction | Completed | 704124 |
Fire Sprinkler Rough-In | 2/4/2022 | D.Meneses | 2/4/2022 9:22:00 AM | Partial | Completed | 699698 |
Fire Sprinkler Rough-In | 1/24/2022 | D.Meneses | 1/24/2022 10:34:00 AM | Partial | Completed | 697198 |
Fire Sprinkler Rough-In | 12/28/2021 | D.Meneses | 12/28/2021 9:32:00 AM | Partial | Completed | 695732 |
Fire Sprinkler Rough-In | 12/14/2021 | D.Meneses | 12/14/2021 1:43:00 PM | Partial | Completed | 695356 |
Fire Sprinkler Rough-In | 12/10/2021 | D.Meneses | 12/10/2021 10:24:00 AM | Correction | Completed | 694997 |
Fire Sprinkler Rough-In | 12/8/2021 | D.Meneses | 12/8/2021 10:04:00 AM | Partial | Completed | 694326 |
Fire Sprinkler Rough-In | 12/2/2021 | D.Meneses | 12/2/2021 2:09:00 PM | Partial | Completed | 693829 |
Fire Sprinkler Rough-In | 11/30/2021 | D.Meneses | 11/30/2021 10:01:00 AM | Partial | Completed | 693654 |
Fire Sprinkler Rough-In | 11/24/2021 | D.Meneses | 11/24/2021 11:32:00 AM | Cancel | Completed | 692592 |
Fire Sprinkler Rough-In | 11/15/2021 | D.Meneses | 11/15/2021 9:36:00 AM | Partial | Completed | 692407 |
Fire Sprinkler Rough-In | 11/12/2021 | D.Meneses | 11/12/2021 7:23:00 AM | Cancel | Completed | 683577 |
Fire Sprinkler Rough-In | 9/17/2021 | D.Meneses | 9/17/2021 2:18:00 PM | Partial | Completed | 679987 |
Fire Sprinkler Rough-In | 8/31/2021 | M.Warren | 8/31/2021 10:56:00 AM | Partial | Completed | 679654 |
Fire Sprinkler Rough-In | 8/23/2021 | D.Meneses | 8/23/2021 8:40:00 AM | Partial | Completed | 677968 |
Fire Sprinkler Rough-In | 8/17/2021 | D.Meneses | 8/17/2021 9:36:00 AM | Partial | Completed | 660269 |
Sprinkler Hydrostatic Test | 2/16/2022 | M.Warren | 2/17/2022 7:25:36 AM | Approved | Completed | 701061 |
Sprinkler Hydrostatic Test | 2/4/2022 | D.Meneses | 2/4/2022 9:18:00 AM | Partial | Completed | 699697 |
Sprinkler Hydrostatic Test | 1/24/2022 | D.Meneses | 1/24/2022 10:28:00 AM | Partial | Completed | 697191 |
Sprinkler Hydrostatic Test | 12/28/2021 | D.Meneses | 12/28/2021 9:11:00 AM | Partial | Completed | 695729 |
Sprinkler Hydrostatic Test | 12/14/2021 | D.Meneses | 12/14/2021 1:37:00 PM | Partial | Completed | 695354 |
Sprinkler Hydrostatic Test | 12/10/2021 | D.Meneses | 12/10/2021 10:16:00 AM | Partial | Completed | 694995 |
Sprinkler Hydrostatic Test | 12/8/2021 | D.Meneses | 12/8/2021 9:52:00 AM | Partial | Completed | 694325 |
Sprinkler Hydrostatic Test | 12/2/2021 | D.Meneses | 12/2/2021 2:00:00 PM | Partial | Completed | 693831 |
Sprinkler Hydrostatic Test | 11/30/2021 | D.Meneses | 11/30/2021 9:55:00 AM | Partial | Completed | 693653 |
Sprinkler Hydrostatic Test | 11/24/2021 | D.Meneses | 11/24/2021 11:31:00 AM | Cancel | Completed | 692587 |
Sprinkler Hydrostatic Test | 11/15/2021 | D.Meneses | 11/15/2021 9:30:00 AM | Partial | Completed | 692405 |
Sprinkler Hydrostatic Test | 11/12/2021 | D.Meneses | 11/12/2021 7:22:00 AM | Cancel | Completed | 683561 |
Sprinkler Hydrostatic Test | 9/17/2021 | D.Meneses | 9/17/2021 2:09:00 PM | Partial | Completed | 679978 |
Sprinkler Hydrostatic Test | 8/31/2021 | M.Warren | 8/31/2021 10:29:00 AM | Partial | Completed | 660268 |