Date | Status | Code | Description | Ref | Location | Comments |
8/17/2021 | Transfer | FireSprinkRough1 | Correction(s) #1 | Correct the following item(s): | | Inspection for 2nd & 3rd floor, Corridors only of the west half of building. Pipe was installed but not no pressure. Piping installation okay will be tested later. contractor understands that there could be leaks. Area is okay to proceed. |