Permit Number: C22-1319
Permit Type: COMMBLDG - BldgAlter - None
Address: 239 W 4TH AVE
Location:
Work Description: EPLANS - T/I TO INCLUDE MEP - ADB
ELECTRONIC FOLDER - SEE ATTACHMENTS
**MECHANICAL SCOPE OF WORK REMOVED ON X24-1259 - BWP**
Parcel: 00210446000
Legal: ORIGINAL BLK 23A LTS 1 2B 4A 5A 6A 9A G:1230
Status: Issued

Subpermit Applications
Permit #Work TypeSub WorktypeProject NameStatusView Permit
E22-1317ElectricalNewChild of Bldg App C22-1319IssuedInfo/Reviews/Inspections
M22-1268MechanicalNewChild of Bldg App C22-1319OpenInfo/Reviews/Inspections
P22-1267PlumbingNewChild of Bldg App C22-1319IssuedInfo/Reviews/Inspections
F23-1295FireAlterationEPLANS-239 W 4TH AVE-FIRE SPRINKLER SYSTEMIssuedInfo/Reviews/Inspections
F22-1425FireAlterationEPLANS- AVIATOR HOTELIssuedInfo/Reviews/Inspections

Inspections

Click Here to Add An Inspection Not Listed

Inspection TypeScheduledAssigned ToCompleted DateResultSchedule InspectionInspection No.
Ceiling / Act2/20/2025B.Gilgus2/20/2025 11:18:24 AMApprovedCompleted842574
Ceiling / Act4/2/2024B.Gilgus4/2/2024 1:45:40 PMApprovedCompleted798544
Final Fire Inspection    Schedule Inspection842821
Final Fire Inspection2/21/2025N.Thomson2/21/2025 1:09:49 PMPartialCompleted821427
Final Fire Inspection8/23/2024M.Panilo8/23/2024 12:00:00 AMPartialCompleted820032
Final Fire Inspection8/16/2024D.Meneses8/16/2024 10:30:00 AMCondApprCompleted819035
Final Fire Inspection8/14/2024M.Panilo8/14/2024 12:00:00 AMPartialCompleted818256
Final Fire Inspection8/9/2024B.Meinhardt8/9/2024 2:54:00 PMCondApprCompleted817950
Final Fire Inspection4/19/2024B.Meinhardt4/19/2024 2:14:00 PMCondApprCompleted713818
Final Structural    Schedule Inspection842794
Final Structural2/21/2025B.Gilgus2/21/2025 10:17:29 AMPartialCompleted819954
Final Structural8/22/2024P.Calhoun8/22/2024 9:04:39 AMPartialCompleted819856
Final Structural8/16/2024P.Calhoun8/16/2024 8:57:32 AMApprovedCompleted817963
Final Structural8/14/2024P.Calhoun8/14/2024 8:40:08 AMPartialCompleted800924
Final Structural8/9/2024P.Calhoun8/9/2024 2:07:40 PMPartialCompleted817959
Final Structural8/9/2024P.Calhoun8/9/2024 2:04:24 PMCancelCompleted817960
Final Structural4/19/2024J.Bergstrom4/19/2024 3:12:37 PMPartialCompleted753489
Fire Rated Wall(s)2/20/2025B.Gilgus2/20/2025 11:14:35 AMApprovedCompleted842575
Fire Rated Wall(s)10/30/2024J.Sooter10/30/2024 10:37:27 AMApprovedCompleted830809
Fire Rated Wall(s)5/10/2024B.Gilgus5/10/2024 8:43:35 AMApprovedCompleted797938
Fire Rated Wall(s)3/28/2024B.Gilgus3/28/2024 9:55:25 AMApprovedCompleted797935
Fire Rated Wall(s)3/28/2024B.Gilgus3/28/2024 7:30:12 AMCancelCompleted797937
Fire Rated Wall(s)10/31/2023B.Gilgus10/31/2023 9:33:14 AMApprovedCompleted783195
Fire Rated Wall(s)9/15/2023thomas.green9/15/2023 11:21:17 AMApprovedCompleted755971
FireStopping2/20/2025B.Gilgus2/20/2025 11:16:48 AMApprovedCompleted842573
FireStopping12/9/2024P.Calhoun12/9/2024 1:24:58 PMApprovedCompleted834924
FireStopping10/17/2024P.Calhoun10/17/2024 9:25:13 AMApprovedCompleted828556
FireStopping7/26/2024P.Calhoun7/26/2024 12:23:53 PMApprovedCompleted810190
FireStopping6/20/2024J.Bergstrom6/20/2024 12:50:57 PMProgressCompleted809974
FireStopping5/3/2024P.Calhoun5/3/2024 2:20:12 PMApprovedCompleted802997
FireStopping5/2/2024P.Calhoun5/2/2024 10:29:43 AMApprovedCompleted802783
FireStopping3/15/2024P.Calhoun3/15/2024 2:49:59 PMApprovedCompleted796337
FireStopping3/14/2024P.Calhoun3/14/2024 2:48:40 PMApprovedCompleted796086
FireStopping3/13/2024P.Calhoun3/13/2024 1:22:08 PMCorrectionCompleted795877
FireStopping1/12/2024P.Calhoun1/12/2024 9:13:13 AMApprovedCompleted789843
FireStopping1/11/2024P.Calhoun1/11/2024 9:54:30 AMCorrectionCompleted789759
FireStopping12/8/2023P.Calhoun12/8/2023 9:53:54 AMApprovedCompleted784723
FireStopping11/14/2023P.Calhoun11/15/2023 9:29:38 AMCorrectionCompleted784492
FireStopping9/15/2023thomas.green9/15/2023 11:20:16 AMApprovedCompleted772463
FireStopping8/11/2023J.Bergstrom8/11/2023 12:41:49 PMPartialCompleted772461
FireStopping4/18/2023P.Calhoun4/18/2023 9:30:19 AMApprovedCompleted751727
FireStopping3/13/2023P.Calhoun3/13/2023 10:28:00 AMCorrectionCompleted751602
Framing    Schedule Inspection753618
Framing3/28/2023P.Calhoun3/28/2023 2:25:45 PMCancelCompleted753447
Framing / Int.3/20/2024P.Calhoun3/20/2024 8:37:53 AMApprovedCompleted796784
Insulation / Vapor Barrier    Schedule Inspection772462
Insulation / Vapor Barrier8/11/2023J.Bergstrom8/11/2023 12:39:08 PMCancelCompleted772365
Other Structural2/20/2025B.Gilgus2/20/2025 8:45:36 AMNACompleted842463
Other Structural1/14/2025J.Bergstrom1/14/2025 2:10:23 PMApprovedCompleted830808
Other Structural12/23/2024P.Calhoun12/23/2024 9:47:43 AMApprovedCompleted836751
Other Structural10/30/2024J.Sooter10/30/2024 10:32:29 AMCancelCompleted830720
Other Structural8/9/2024P.Calhoun8/9/2024 2:04:57 PMApprovedCompleted817754
Other Structural8/5/2024P.Calhoun8/5/2024 1:16:56 PMApprovedCompleted816858
Other Structural8/2/2024P.Calhoun8/2/2024 1:05:11 PMApprovedCompleted816664
Other Structural8/1/2024P.Calhoun8/1/2024 9:01:41 AMApprovedCompleted816396
Other Structural7/16/2024J.Bergstrom7/16/2024 3:08:50 PMApprovedCompleted813781
Other Structural7/3/2024P.Calhoun7/3/2024 9:00:08 AMApprovedCompleted812102
Other Structural5/23/2024P.Calhoun5/23/2024 9:05:36 AMApprovedCompleted805839
Other Structural5/13/2024P.Calhoun5/13/2024 9:17:56 AMApprovedCompleted797906
Other Structural2/14/2024P.Calhoun2/14/2024 1:46:49 PMApprovedCompleted783196
Other Structural10/31/2023B.Gilgus10/31/2023 8:37:29 AMCancelCompleted783110
Other Structural10/27/2023J.Bergstrom10/27/2023 1:47:41 PMApprovedCompleted773431
Other Structural8/18/2023J.Bergstrom8/18/2023 10:01:16 AMPartialCompleted773266
Other Structural5/4/2023P.Calhoun5/4/2023 9:27:41 AMApprovedCompleted757901
Other Structural4/18/2023P.Calhoun4/18/2023 9:33:53 AMApprovedCompleted755876
Other Structural4/14/2023P.Calhoun4/14/2023 8:29:47 AMCancelCompleted752146
Other Structural4/4/2023P.Calhoun4/4/2023 9:17:12 AMApprovedCompleted754361
Other Structural3/16/2023P.Calhoun3/16/2023 3:05:17 PMApprovedCompleted713817
Other Structural3/15/2023P.Calhoun3/15/2023 2:19:30 PMCorrectionCompleted751753

Reviews

SINCE THIS IS AN EPLANS REVIEW, PLEASE GOTO EPLANS TO SEE THE REVIEW COMMENTS
Click here to goto ePlans
Don't have an ePlans account? Click here.

Review TypeReview NumberCompleted by:Completed Date:ResultComments
Architectural3L.Bergstrom5/12/2022Approved
Architectural2L.Bergstrom5/11/2022Correction
Architectural1L.Bergstrom4/11/2022Correction
Electrical1D.Abuobaid4/7/2022ApprovedView Comments
Fire1M.Warren5/12/2022Approved
Mechanical1L.Bergstrom4/12/2022Approved
Plumbing2L.Bergstrom5/11/2022Approved
Plumbing1L.Bergstrom4/12/2022Correction
Zoning1T.Barganier4/14/2022Approved

Permit Contacts
TypeName PhoneEmailPrimary Permittee?
OtherTHOMPSONKAYLI scopepne.kayli@gmail.comN
Property OwnerALASKA HOTEL GROUP   Y

Change Orders
Permit #Work TypeSub WorktypeProject NameStatusView Change Order
X22-1413BldgAlterChangeOrdrChange Order of Bldg App C22-1319CancelledInfo/Reviews/Inspections
X24-1569BldgAlterChangeOrdrEPLANS - Change Order of Bldg App C22-1319ClosedInfo/Reviews/Inspections
X24-1239BldgAlterChangeOrdrChange Order of Bldg App C22-1319ClosedInfo/Reviews/Inspections
X24-1259BldgAlterChangeOrdrEPLANS - Change Order of Bldg App C22-1319ClosedInfo/Reviews/Inspections
X24-1560BldgAlterChangeOrdrChange Order of Bldg App C22-1319ClosedInfo/Reviews/Inspections
X24-1235BldgAlterChangeOrdrEPLANS - Change Order of Bldg App C22-1319ClosedInfo/Reviews/Inspections