Project Name: C21-1153 Project Description: EPLANS- CANDLEWOOD SUITES/HOLIDAY INN EXPRESS Review Comments List Date: 8/17/2021
Ref. # 97, 4/27/21 5:16 PM, Cycle 1
Markup: Struc 22, S2.0B.pdf
Please provide the size and details of footings and framing required for this canopy.
Ref. # 158, 8/17/21 3:43 PM, Cycle 3
Comment:
Please provide a drawing set with all plans marked "For Construction."
Ref. # 160, 8/17/21 3:50 PM, Cycle 3
Markup: Struc 38, S3.0B.pdf
It is not clear how the roof framing members are supported at the corner overhang; please provide framing connections or hangers.
Ref. # 161, 8/17/21 3:55 PM, Cycle 3
Markup: Struc 37, S3.0A.pdf
Please clarify the force transfer around diaphragm openings mechanism per the requirements of ASCE 7.
Ref. # 162, 8/17/21 4:00 PM, Cycle 3
Markup: Struc 39, S3.5.pdf
Architectural sheet A539 shows a different detail; please clarify.
Ref. # 163, 8/17/21 4:03 PM, Cycle 3
Markup: Struc 40, S6.1.pdf
Please provide a connection for out-of-plane wall forces at the top of the walls.
Ref. # 164, 8/17/21 4:04 PM, Cycle 3
Markup: Struc 41, S8.1.pdf
Please provide a connection to brace the wall for out-of-plane forces.
Ref. # 165, 8/17/21 4:06 PM, Cycle 3
Markup: Struc 42, S9.1.pdf
Pleas provide a shear transfer connection from the roof diapragm to the wall.