Permit Number: C21-1153
Permit Type: Commercial Building Permit - None BldgNew
Address: W 160 48TH AVE Anchorage
Location: 160 W 48th Ave
Work Description: EPLANS-117094 SQFT, TYPE VB, OCCUPANCY R-1-GJS
NO CCO ON THIS PERMIT UNTIL SHARED ACCESS WITH C15-1806 IS RESOLVED. JCA 6/19/23 Resolved with change order X22-1625. JCA 8/13/24

**REVOKED MAIN PERMIT AND ISSUED CORE AND SHELL ONLY PER JUDY 6/19/23 - SEE HER COMMENTS UNDER PD CIVIL REVIEW - BWP**
Change order X22-1625 has been approved and this permit (C21-1153) has full PD Civil approval.  - RDO (Per PDCivil Final Review)
***PHIL CALHOUN OKAYED A SATURDAY INSPECTION FOR 8/3/24 FOR INSUL/VAPOR BARRIER; PAID $800 FOR SATURDAY INSPECTION*** CCK 8/2/24
***JESSE SOOTER OKAYED SATURDAY INSPECTION FOR 11/23/24 FOR SHEETROCK SCREW PATTERN FOR 4TH FLOOR- CCK 11/22/24
Status: Issued
Project Name: EPLANS- CANDLEWOOD SUITES/HOLIDAY INN EXPRESS
Review Type: Structural
Result: FandF
Result Date: 8/17/2021 4:11:00 PM

Comments:

 Code SectionReview CommentStatus



Advisory Information:

STRUCTURAL REVIEW COMMENTS

Project Name: C21-1153
Project Description: EPLANS- CANDLEWOOD SUITES/HOLIDAY INN EXPRESS

Review Comments List Date: 8/17/2021


Ref. # 97, 4/27/21 5:16 PM, Cycle 1


Markup: Struc 22, S2.0B.pdf


Please provide the size and details of footings and framing required for this canopy.


 


Ref. # 158, 8/17/21 3:43 PM, Cycle 3


Comment:


Please provide a drawing set with all plans marked "For Construction."


 


Ref. # 160, 8/17/21 3:50 PM, Cycle 3


Markup: Struc 38, S3.0B.pdf


It is not clear how the roof framing members are supported at the corner overhang; please provide framing connections or hangers.


 


Ref. # 161, 8/17/21 3:55 PM, Cycle 3


Markup: Struc 37, S3.0A.pdf


Please clarify the force transfer around diaphragm openings mechanism per the requirements of ASCE 7.


 


Ref. # 162, 8/17/21 4:00 PM, Cycle 3


Markup: Struc 39, S3.5.pdf


Architectural sheet A539 shows a different detail; please clarify.


 


Ref. # 163, 8/17/21 4:03 PM, Cycle 3


Markup: Struc 40, S6.1.pdf


Please provide a connection for out-of-plane wall forces at the top of the walls.


Ref. # 164, 8/17/21 4:04 PM, Cycle 3


Markup: Struc 41, S8.1.pdf


Please provide a connection to brace the wall for out-of-plane forces.


 


Ref. # 165, 8/17/21 4:06 PM, Cycle 3


Markup: Struc 42, S9.1.pdf


Pleas provide a shear transfer connection from the roof diapragm to the wall.