| Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
| Fire Sprinkler Bracing Final | | | | | Schedule Inspection | 831528 |
| Fire Sprinkler Bracing Final | 11/5/2024 | D.Meneses | 11/5/2024 2:37:00 PM | Partial | Completed | 827079 |
| Fire Sprinkler Bracing Final | 10/4/2024 | M.Panilo | 10/4/2024 4:17:00 PM | Partial | Completed | 751978 |
| Fire Sprinkler Final | 5/8/2026 | D.Meneses | 5/8/2026 1:47:00 PM | Approved | Completed | 853577 |
| Fire Sprinkler Final | 5/8/2025 | | 5/8/2025 2:12:33 PM | Partial | Completed | 848706 |
| Fire Sprinkler Final | 4/7/2025 | D.Meneses | 4/7/2025 11:40:00 AM | Partial | Completed | 846593 |
| Fire Sprinkler Final | 3/21/2025 | B.Meinhardt | 3/21/2025 3:37:00 PM | Correction | Completed | 841527 |
| Fire Sprinkler Final | 2/10/2025 | D.Meneses | 2/10/2025 11:21:00 AM | Partial | Completed | 790395 |
| Fire Sprinkler Final | 1/18/2024 | M.Panilo | 1/18/2024 12:56:00 PM | Partial | Completed | 751975 |
| Fire Sprinkler Rough-In | 5/2/2025 | M.Panilo | | | View Scheduled Inspection | 831531 |
| Fire Sprinkler Rough-In | 11/5/2024 | D.Meneses | 11/5/2024 2:44:00 PM | Partial | Completed | 827081 |
| Fire Sprinkler Rough-In | 10/4/2024 | M.Panilo | 10/4/2024 4:20:00 PM | Partial | Completed | 786961 |
| Fire Sprinkler Rough-In | 12/6/2023 | M.Panilo | 12/7/2023 5:22:00 PM | Partial | Completed | 751977 |
| Sprinkler Hydrostatic Test | 5/2/2025 | M.Panilo | | | View Scheduled Inspection | 848705 |
| Sprinkler Hydrostatic Test | 10/4/2024 | M.Panilo | | Cancel | Completed | 751976 |
| Sprinkler Hydrostatic Test | 4/7/2025 | D.Meneses | 4/7/2025 11:33:00 AM | Cancel | Completed | 831526 |
| Sprinkler Hydrostatic Test | 11/5/2024 | D.Meneses | 11/5/2024 2:30:00 PM | Partial | Completed | 828921 |
| Sprinkler Hydrostatic Test | 10/17/2024 | D.Meneses | 10/17/2024 3:23:00 PM | Partial | Completed | 827077 |