REMOVE AND REPLACE SALES FLOOR COOLER IN SAME LOCATION-GJS
PERMIT FEE TO BE PAID UPON ISSUANCE-GJS
COMPRESSOR
Reference the compressor replacement design. Please provide design of the new compressor’s anchorage for seismic forces per ASCE 7-05, Chapter 13. This item can be deferred.
Comment remains. It doesn't appear as if a response has been provided. Will this item be deferred? WAB - 6/25/2015
MOMENT FRAME
Reference detail 12 on sheet 141925-D of the drawings. Single sided fillets or partial penetration welds are not permitted to be used to resist tension due to seismic forces per AISC 341-05 section 11.2a(3). These connections must be designed for an R=1 (maximum force that can be delivered by the system) or 1.1*Ry*Mp of the column or beam whichever is smallest. Reference AISC 341-05 section 11.2a.
Comment remains. No new drawings have been provided with a revised moment frame connection. It appears that single sided fillet welds are still shown on the drawings. See the detail referenced by the original comments. WAB - 6/25/2015
ANCHORAGE AT FRAMES
The anchorage at frames must meet ACI 318-05 Appendix D including the ductile or non ductile yielding requirements of sections D3.3.4 through D3.3.6.
Comment resolved. The calculation that has been provided doesn't include a non ductile yielding factor, but appears to be stressed very low so it shouldn't make a difference. WAB - 6/25/2015
USE OF ANTHONY DOOR FRAMES
Reference the design. The design calls for the use of Anthony Door Frames for lateral resistance in the long direction. Please provide substantiating data showing these frames are acceptable. The test data provided appears to cover a specific height, and can not be readily adapted to the much taller height on this project. It’s possible another system is being used since there appears to be HSS 4X4 seismic columns called out in the details, but this isn’t clear from the design. Please indicate the frames on the drawings including all material specifications, connections, etc. Reference AAC section 23.10.104.8 and IBC section 1703.4.
Comment remains. It appears the calculations indicate that cantilever columns are being used to transfer the seismic forces. Please verify that this is the case. It also doesn't appear as if the material specifications for all materials used on the project has been indicated. Please provide. WAB - 6/25/2015
STATEMENT OF SPECIAL INSPECTIONS
Please provide a statement of special inspections as required by IBC section 1705. The statement of special inspections must include both the type and frequency of inspection.
Comment resolved. Response accepted. A statement of special inspection has now been included. WAB - 6/25/2015
SPECIAL INSPECTORS
Please provide a letter from the Owner indicating who they will be hiring to provide the special inspections for this project. The special inspectors must be licensed by MOA in the types of inspections to be performed. Reference IBC section 1703.1.
Comment remains. No response provided. WAB - 6/25/2015
Reviewed by: Bolen, Wayne A. Permit #: C15-1020
Phone: 343-8072 Date: 6/25/2015
Fax: 249-7393
Email: BolenWA@muni.org
Permit Manager: Tony Barganier
Phone: 343-8339
Email: BarganierTA@muni.org
Project: Costco #10 Cooler Box
Review Number: 353792
____________________________________________________________________________________
PERMIT STATUS
3/9/2015 – Review complete. Comments issued.
6/25/2015 - Responses reviewed. Comments issued.
Advisory Comment (no response required): This review is based on the requirements of the Anchorage Administrative Code (AAC), 2009 International Building Code (IBC), 2009 International Residential Code (IRC) and all adopted references thereto as amended by MOA. The following comments must be addressed before a permit can be issued. The approval of plans and specifications does not permit the violation of the codes, or any federal, state or local regulations.
Please provide a written response to the comments and include one copy of additional or revise calculations, and two copies of additional or revise drawings.
All submittals should be sent to the permit manager.