| Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
| Final Structural | 2/21/2025 | J.Bergstrom | 2/21/2025 9:19:56 AM | Approved | Completed | 810328 |
| Final Zoning | 6/24/2025 | M.Radovan | 6/24/2025 11:39:00 AM | Approved | Completed | 855609 |
| Final Zoning | 5/22/2025 | M.Goldstein | 5/22/2025 12:00:00 AM | Cancel | Completed | 843245 |
| Final Zoning | 2/26/2025 | M.Goldstein | 2/26/2025 12:00:00 AM | Cancel | Completed | 842777 |
| Final Zoning | 2/21/2025 | | 2/21/2025 8:51:00 AM | Cancel | Completed | 839485 |
| Private Development Site Civil | 2/21/2025 | S.Ellis | 6/24/2025 11:55:00 AM | Approved | Completed | 810330 |
| StormWater Inspection-Annual | 2/21/2025 | | 6/24/2025 11:59:00 AM | Approved | Completed | 810331 |