EPLANS - NEW 16,918 SQ FT THREE STORY OFFICE BUILDING - TYPE IIB CONSTRUCTION - B = 10176 SQ FT, A-3 = 2400 SQ FT, AND PARKING GARAGE = 4342 SQ FT - BWP
ELECTRONIC FOLDER/DOCS IN ATTACHMENTS - BWP
**OKAY TO ISSUE FILL/GRADE PERMIT ONLY PER ROSS NOFFSINGER 10/31/2022. BWP**
FINAL P/M/E /STRUCTURAL / ZONING INSPECTIONS & ROW COMMENTS PRINTED & IN ATTACHMENTS (WAITING ON FINAL FIRE INSPECTIONS AND FINAL AS BUILT***CCK 4/30/24
Hours of operation for construction.
///10/27/22 see sheet C001. tb
Please provide the building dimensions on the plot plan.
///10/27/22 sheet V103 is not loaded in Eplans. tb
21.04.060D.2. Applicants for allowed uses as listed in 21.05-1 shall demonstrate, to the satisfaction of the director, that they are water-dependent and/or water related, before applying for any required permits are entitlements. Please provide director's approval.
/10/27/22 see director's approval. tb
Fee will be charged once parking requirement has been determined.
///10/27/22 fee will be required for (29) parking spaces. tb