REPLACEMENT OF THE TWO GAS FIRED BOILERS AND MAIN CIRCULATION PUMPS. THE TELECOM ROOM AIR CONDIDTIONING SYSTEM WILL ALSO BE REPLACED. SEISMIC RESTRAINT AND ANCHORING DESIGN FOR THE NEW EQUIPMENT - MJD
COVID-19 25% DISCOUNT APPLIED
Reviewed by: Bergstrom, Leigh W.
Phone: 343-8326
Fax: 249-7615
Email: BergstromLW@muni.org
Permit Manager: Melissa Davidson
Phone: 343-8339
Email: DavidsonMJ@muni.org
Project: UNIVERSITY OF ALASKA MECHANICAL UPGRADES
Review Number: 449377
1) Provide structural, seismic and wind load calculations, as applicable, plus fastening details for PMP-B1 & B2, PMP-1A & 1B, AS-1, AC-1A & 1B and BLR-1 & 2 to include the engineers stamp and signature, for structural review on a deferred submittal basis. MECHANICAL IS APPROVED AS OF 6-01-2020.