Reviewed by: Bergstrom, Leigh W.
Phone: 343-8326
Fax: 249-7615
Email: BergstromLW@muni.org
Permit Manager: Andrew Earp
Phone: 343-8338
Email: Earpal@muni.org
Project: GATE TECHNOLOGY PROJECT-PORT OF ANCHORAGE
Review Number: 394978
1) STATUS: 7-12-2017 Comments to be addressed. 8-01-2017 COMMENTS TO BE ADDRESSED.
2) The following comments based upon the 2012 International Building, Mechanical and Fuel Gas Codes must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the IBC, IMC, IFGC or any federal, state or local regulations. RESOLVED 8-01-2017.
3) M2.1 thru M2.3 Provide details for the GS & GR to the manifolds. (Pipe material, utilidor or buried, how deep, pipe insulation?) 7-01-2017 UNRESOLVED. THE RESPONSE INFORMATION MUST BE ADDED WITHIN THE PLAN SET.
4) M2.4 Boilers shall be mounted on floors of non-combustible construction, unless listed for mounting on combustible flooring (IMC 1004.5). Please clarify. RESOLVED PER RE-SUBMITTAL RECEIVED 7-27-2017.
5) M4.0 A note requires the boiler condensate to a drywell drain (see civil). The civil drawings did not appear to have any drywell information. Please clarify. 8-01-2017 UNRESOLVED. THERE ARE NO REVISED CIVIL DRAWINGS WITHIN THE PLAN SET.
6) M4.0 Provide details for the condensate pipe routing to the drywells and the required freeze protection per UPC 3312.6. RESOLVED PER RE-SUBMITTAL RECEIVED 7-27-2017.
7) M4.1 Provide manifold piping details to include access and weather protection. RESOLVED PER RE-SUBMITTAL RECEIVED 7-27-2017.
8) M4.1 Provide snowmelt piping information for each area such as pipe size, tubing lengths, spacing, number of loops, GPM, pressure drops, etc. RESOLVED PER RE-SUBMITTAL RECEIVED 7-27-2017.
9) M4.1 Provide tubing manufacturer's details showing recommended insulation, fastening to cement reinforcing material and control joint (CJ) passage. RESOLVED PER RE-SUBMITTAL RECEIVED 7-27-2017.
10) When the above comments have been addressed, please update the plans at the MOA Plans Review Office with three sets of revised mechanical pages to include clouded changes, engineers stamp and signature. RE-SUBMITTALS ARE TO BE DIRECTED TO THE ATTENTION OF THE PERMIT MANAGER WITH A LETTER OF RESPONSE ADDRESSING EACH COMMENT. (23.10.104.8.1)