INSTALLING NEW EQUIPMENT FOUNDATION 668 SQFT 11B UTILITY, PIPE RACKS AND PIPING, NEW TRUCK RACK FRAME AND FOUNDATION AND A NUMBER OF KIOSKS - MJD
6/29/2017: REMOVE PIPE SUPPORTS FROM SCOPE OF WORK - MJD
6/30/2017: READDED PIPE SUPPORT TO SCOPE OF WORK - BWP
Comments on 6/28/17 submittal
1. The drawings submitted were structural sheets only for new truck rack. Provide a site plan for this portion of the dock that shows location of this truck rack in relation shop to tanks and buildings to determine circulation requirements for this new structure.
Traffic comments are incomplete pending submission of additional information. Additional Comments may be generated. 6-30-17~RR