Electrical Comments
Reviewed by: David Abuobaid Permit#: C17-1398
Phone: 343-8333 Date: 5/4/2017
Fax: 249-7775
Email: AbuobaidDH@muni.org
Permit Manager: AndrewEarp
Phone: 343-8338
Email: EarpAL@muni.org
Project: Well FargoATM (Fax: no fax provided)
________________________________________________________________________________
1.The following comments based on the 2014 National Electrical Code (NEC) must beresolved before a permit is issued. The approval of plans and specificationsdoes not permit the violation of any section of the NEC or any federal, stateor local regulations.
2. REQUIREMENT OF ELECTRICALWORK;Please provide 100% engineered electrical drawings by a registeredprofessional electrical engineer in the State of Alaska. The design shallinclude:
Panelschedule with existing and new circuits, connected load and NEC demand load.
Existing service loadcalculations as required per NEC 220.87.
Panel feeder (250 feetlong?), Circuit homerun and voltage drop calculations.
Owner (Wells Fargo) siteplan (sheet 1 of 7) shows three new circuits 30 Amp and 2 circuits 20 Amps.General electrical note shows two 20 amps circuits. Which ones are intended tobe used?
The new light pole, feed and circuitry.
Does the new walk-up ATM building have heat?
3. When the above comments have been addressed,please update the electrical plans at the MOA Plans Review Office with three(3) sets of revised electrical pages to include clouded changes, electricalengineers stamp and signature.