RETAIL STORE-TENANT IMPROVEMENT TO INCLUDE A, P, M, AND E.
CONTRACTOR TO PAY FOR INSPECTIONS-SP. ***5/31/19 per Aaron Kiezer w/ Famous Footwear 314-873-8921 they never moved spaces at mall so cancel this permit... no refund*** 6/4/19 slo
Reviewed by: Bergstrom, Leigh W.
Phone: 343-8326
Fax: 249-7615
Email: BergstromLW@muni.org
Permit Manager: Sean Palmer
Phone: 343-8181
Email: PalmerSP@muni.org
Project: FAMOUS FOOTWARE
Review Number: 379105
1) STATUS: 9-09-2016 Comments to be addressed.
2) The following comments based upon the 2012 International Building, Mechanical and Fuel Gas Codes must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the IBC, IMC, IFGC or any federal, state or local regulations.
3) Provide approved structural, seismic and wind load calculations, as applicable, plus fastening details for AHU-1 thru 4 and HPCU-2 to include engineers stamp and signature, for structural review on a deferred submittal basis.
4) Provide an equipment schedule for HPCU-2.
5) M2.0 Outside Air Schedule The MOA is currently reviewing under the 2012 adopted codes, not the 2009. NO RESPONSE REQUIRED.
6) When the above comments have been addressed, please update the plans at the MOA Plans Review Office with three sets of revised mechanical pages to include clouded changes, engineers stamp and signature. RE-SUBMITTALS ARE TO BE DIRECTED TO THE ATTENTION OF THE PERMIT MANAGER WITH A LETTER OF RESPONSE ADDRESSING EACH COMMENT. (23.10.104.8.1)