OK for Footing & Foundation ONLY, MG 6-8-15. Other grading work outside of the building footprint such as storm drain and final grading are not approved. By the developer going forward with the F&F the floor elevation will be set prior to approval of a grading & drainage plan stamped by a civil engineer that may result in significant increased costs to the developer to resolve site specific challenges to preparing an approvable site grading & drainage plan.
Correction, MG 6-8-15, 6-23-15. 7-7-15.
1. Ref. C2.0; Please clarify where the swale that runs north along the west property line discharges into a drainage facility. "Proposed drainage systems shall convey drainage into an established natural watercourse or an existing storm drainage facility" DCM 2.2.D.6. Resolved, MG 6-23-15.
2. PDCIVIL comments may be incomplete pending further submittals.
3. Ref. C2.0, 12" CPEP connection to 36" CMP; A manhole shall be installed at major junctions places where there are changes in vertical or horizontal alignment, and at locations where there are changes in pipe size or shape. 2007 DCM 2.7.D.1. MG 6-23-15. As of 7-2-15; A type I Horseshoe SDMH is proposed. Please submit the special circumstances with defined engineering parameters supporting the non-standard (M.A.S.S.) manhole along with Street Maintenance (Steven Hughes 343-8161) concurrence with the solution. Not Resolved, MG 7-7-15.