AIR HANDELING UNIT
Reference the RAH-ED1 design and details. Whatever is being used for construction needs to be stamped and signed by an engineer licensed in Alaska. Based on what has been provided it is recommended that page1 and the details at the end be stamped and signed. It may be possible to only stamp page 1 as well as it appears all necessary information is on this sheet. Reference the Alaska State Statutes section 08.48.221.
AIR CURTAIN SUPPORT DESIGN
Reference the design of the air curtain support. Air curtains generally generate their own force when active. Please verify that this force is less than the design seismic force. Reference IBC section 1604.4.
Reviewed by: Bolen, Wayne A. Permit #: C14-1805
Phone: 343-8072 Date: 3/24/2015
Fax: 249-7393
Email: BolenWA@muni.org
Permit Manager: Tony Barganier
Phone: 343-8339
Email: BarganierTA@muni.org
Project: Alaska Regional Mechanical Equipment Anchorage
Review Number: 348131
____________________________________________________________________________________
PERMIT STATUS
3/24/2015 – Review complete. Comments issued.
Advisory Comment (no response required): This review is based on the requirements of the Anchorage Administrative Code (AAC), 2009 International Building Code (IBC), 2009 International Residential Code (IRC) and all adopted references thereto as amended by MOA. The following comments must be addressed before a permit can be issued. The approval of plans and specifications does not permit the violation of the codes, or any federal, state or local regulations.
Please provide a written response to the comments and include one copy of additional or revise calculations, and two copies of additional or revise drawings.
All submittals should be sent to the permit manager.