6000 SQFT METAL BLDG, S-2, VB-GJS
PERMIT REASSIGNED TO TOMMY C 8/26/2014-GJS
1. Provide a plot plan showing lowest floor elevation (crawl space, enclosures and basements included) in 1972 NGS msl datum. sme. RESOLVED SME
2. The plot plan provided shows the elevation of the lowest floor in mean lower low water not mean sea level. The surveyor has been contacted and notified of the requirement. sme RESOLVED SME
3. This project requires a separate flood hazard permit. sme. RESOVLED THE PROJECT IS NOT IN THE SFHA. SME
4. The applicant is approved to clear site, demo pavement and excavation. sme
5. The applicant is advised not to do work that is critical to foundation elevation, until the plot plan has provided the lowest floor elevation. To meet our flood hazard requirements the floor must be at or above 21.5 feet msl. sme RESOLVED SME
6. Approved for Footing and Foundation phase of this permit. sme
7. This project is approved for a full permit for flood hazard concerns. sme