Permit Number: C14-1705
Permit Type: Commercial Building Permit - None BldgAdd
Address: 2500 MINNESOTA DR Anchorage
Location:
Work Description: ADDITION AND RENOVATION IN SUPPORT OF CAREER TECHNOLOGY CLASSROOMS AT ROMIG SCHOOL-GJS
Status: Closed
Project Name: WRCTE ADDITIONS AND RENOVATIONS
Review Type: Storm Water
Result: Approved
Result Date: 9/19/2014 9:06:59 AM

Comments:

 Code SectionReview CommentStatus



Advisory Information:

OK for footing and foundation 8/27/2014 PL

 

1.Submit a completed, signed and dated MOA Handout AG.21 Checklist # 2 and # 3. Available on this link: http://www.muni.org/Departments/OCPD/development/BSD/Handouts/handoutag21.pdf

 

 

 

2.Submit a Permanent Storm Water Quality Control Plan- Applicable to new or redevelopment commercial projects. See section 7, STORM WATER TREATMENT GUIDANCE MANUAL 3RD EDITION:  for this requirement. http://www.muni.org/Departments/works/project_management/Documents/SWTPRGM%20Sept2010.pdf

 

 

 

3.Submit an Operation and Maintenance Manual for the permanent storm water treatment controls. See section 8, STORM WATER TREATMENT GUIDANCE MANUAL 3RD EDITION: for this requirement the Plan shall provide more specific guidance for maintenance, operations and inspection of the permanent BMPs, Provide periodic inspection of the parking lot for spills and debris. The parking lot is required to be swept twice per year, By June 15th and Oct 15th. Permanent BMPs are required to be cleaned on the same schedule. Include a statement identifying person(s) who will own, operate, and maintain the proposed system(s)... http://www.muni.org/Departments/works/project_management/Documents/SWTPRGM%20Sept2010.pdf

 

 

4. Certification page for the submitted SWPPP needs to be signed and dated by the operator.

 

 

 

5.Submit a copy of the approved filed APDES Notice of Intent (NOI)

http://dec.alaska.gov/water/wnpspc/stormwater/APDESeNOI.html

 

For construction project disturbing one or more acres or less than one acre but part of a larger common plan of development, the MOA is required under the MS4 permit to verify whether the construction site operator(s) have obtained necessary coverage under the APDES Construction General Permit before issuance of a storm water review approval.

 

 

 

 

Note: This review shall be considered incomplete pending receipt and approval of the requested revisions or additional comments