Corrections Required 6/17/2014 per fire marshall. Requesting further documentation to include a formal code study, building layout (general floor plan), and inspections to verify conditions. (Refer to e-mail sent to architect from fire marshal)
.
Is this an "Alternate Means" rather than a straight "Change Order" since the sprinkler system will not be in strict compliance with the 2009 code for malls. See concern 3 on attached F.I.R.E. Services letter from Ross Fosberg dated 5/14/2014.
Are there any other non-compliance items, no matter how small, that need to be addressed in the request? If yes please add to the submittal and treat as an "Alternate Means".