Comments for 5/8/14 submittal:
1.) GMC export route will be Elmore - Tudor - Minnesota - Raspberry - Lucy Pit. Import is unknown at this time. Some is liely to come from Abbott and Lake Otis via Lake Otis - Dowling - Elmore - site or Sand Lake - Raspberry - Minnesota - Tudor - Elmore - site. Concrete will come from AS&G (South Anchorage) and head north on New Seward Hwy - Tudor - Elmore - site. The primary route to the site will be New Seward Hwy to Tudor - Elmore. Construction hauling and material related deliveries will avoid local and collector roads as much as possible utilizing major roadways.
2.) Approved for on site fill and grade work only. 5/22/12 ~DF~
3.) Approved for footing and foundation work to proceed. 6/15/12 ~DF~
4.) Approved for core and shell work only. 11/8/12 ~DF~
5.) Approved for full buildout. Prior to issuance of any conditional CO or final CO permit, the petitioner shall resolve all outstanding comments listed herein. 11/30/12 ~DF~
6.) Approved as submitted. 5/8/14 ~DF~