TENANT IMPROVEMENT (JINNY ROSE DAY)
REASSIGNED TO BOB PARKER 3/6/2014.
Reviewed by: Bergstrom, Leigh W. Permit #: C13-2162
Phone: 343-8326 Date: 02/12/2014
Fax: 249-7615
Email: BergstromLW@muni.org
Permit Manager: Jinny Day
Phone: 343-8338
Email: DayJR@muni.org
Project: Forever 21
Review Number: 326703
1) STATUS: 01-14-14 Comments to be addressed. 2-12-14 APPROVED.
2) The following comments based on the 2009 International Building, Mechanical and Fuel Gas Codes must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the IBC, IMC, IFGC or any federal, state or local regulations. RESOLVED 2-12-14.
3) Provide structural and seismic calculations plus fastening details for RTU-2 and WH to include engineers stamp and signature, for structural review on a deferred submittal basis. RESOLVED 2-12-14.
4) M1.1.0 & M3.1.0 According to the architectural plans most of the interior walls on the south end of the building are 1-hour assemblies. There appear to be 9 penetrations of rated walls on the first level and seven on the mezzanine level without the required fire dampers. Coordinate with the architect and clarify required fire damper locations. (IBC 716.5.2) RESOLVED PER RESUBMITTAL RECEIVED 2-04-14.
5) When the above comments have been addressed please update the plans at the MOA Plans Review Office with three sets of revised mechanical pages to include clouded changes, engineers stamp and signature. RESUBMITTALS ARE TO BE DIRECTED TO THE ATTENTION OF THE PERMIT MANAGER WITH A LETTER OF RESPONSE ADDRESSING EACH COMMENT. RESOLVED 2-12-14.