17,942 SQ FT ADD'N & $7,901,250 COMM T/I / TB
9/23/2014 PAID $4800 IN PAST DUE FEES, AND $ 5200 IN FUTURE FEES-GJS
12/24/2014 paid $8850 for 59 inspections plus picked up change orders.BWP
Comments for 1/8/14 submittal:
1.) Identify all haul routes for demolition, material sources and disposal sites including frequency and types of proposed maintenance of haul routes and emergency telephone contact persons. List the days and hours of haul route use and submit temporary Traffic Control Plan (TCP) for sidewalk work on 4th Avenue and the hydrant, water service and sewer installation operations along "G" Street and the unnamed alley. The shortest, most direct route, which minimizes travel on local and collector roadways shall be used.
2.) Provide sign schedule and installation detail for the existing signs or appurtenances to be removed and replaced for construction of the proposed heated aggregate sidewalk on 4th Avenue.
3.) This review shall be considered incomplete pending receipt and approval of the requested revisions or additional comments. 1/10/14~DF~