1st Review 10/14/2013 - Corrections Required. Clarify scope of work. see comments below.
.
1. Verify that the elevator lobby is not within the scope of work and that you are maintaining the required lobby separation. It is not clear if your intent is to demo these doors as you are showing them as dashed lines.
2. Sheet G0.2 references a fire rated exit corridor. If the intent is to maintain this rating then doors 1300A & B are required to be rated. Please show rating on the door schedule.
3. Doors 1300A & B appears to alter the natural path of egress. Verify or adjust exit signage accordingly. IE: The path from the N/E corner directs occupants to the same stair rather than to both stairs. The path from the S/W corner appears to do the same.