Permit Number: C13-1562
Permit Type: Commercial Building Permit - None BldgAlter
Address: 5740 DE HAVILLAND AVE Anchorage
Location:
Work Description: CONSTRUCTION OF A DIESEL EXHAUST FLUID STORAGE AND DISPENSING SYSTEM WITH COVER (JINNY ROSE DAY)
Status: Issued
Project Name: ANC DIESEL EXHAUST FLUID SYSTEM
Review Type: Structural
Result: Correction
Result Date: 7/24/2013 11:42:49 AM

Comments:

 Code SectionReview CommentStatus



Advisory Information:

Reviewed by: Bolen, Wayne A.                                                  Permit #: C13-1562

Phone: 343-8072                                                                        Date: 7/24/2013

Fax: 249-7393

Email: BolenWA@muni.org

Permit Manager: Jinny Day

Phone: 343-8338

Email: DayJR@muni.org

Project: ANC Diesel Exhaust Fluid System

Review Number: 316147

____________________________________________________________________________________

 

PERMIT STATUS (no response required) 7/24/2013: Review complete. Comments issued.

 

Advisory Comment (no response required):  This review is based on the requirements of the Anchorage Administrative Code (AAC), 2009 International Building Code (IBC), 2009 International Residential Code (IRC) and all adopted references thereto as amended by MOA. The following comments must be addressed before a permit can be issued. The approval of plans and specifications does not permit the violation of the codes, or any federal, state or local regulations.

 

1. ANCHOR DESIGN

Please provide design of the column anchorage. These anchors have a significant overturning moment of around 31 kip-ft. The spreadsheet for confining shear breakout appears to have been provided, but nothing has been provided for tension. Reference ACI 318-08 Appendix D.

 

2. EQUIPMENT ANCHORAGE

It appears there is a design for equipment anchorage provided; however no detail could be located on the drawings. Please clarify. Reference AAC section 23.10.104.8.

 

3. PARAPET DESIGN

Reference detail 204 in the drawings. Please provide design of the parapet and its connections shown in this detail. Parapets must be designed for the loads required by ASCE 7-05 section 6.5.12.4.4.

 

4. NON FROST PROTECT FOUNDATION

Reference the drawings. A non frost protected slab on grade foundation has been indicated on the drawings. Please provide an alternate means and methods for approval. Please note that flexible connections will need to be provided between the equipment and any other elements supported by a frost protected foundation for this to be approved. Even then it would need to be approved by the Senior Plan Reviewer or Building Official.

 

5. LOAD INPUT ON FOUNDATION

Reference page 14 of the RISA model. It isn’t clear where the moment from the snow load when snow is loaded on one span only has been inputted. Please clarify where this load is. Under the strength load combination please note that this is a flat roof structure, and the roof will retain snow so the load factor should be taken as 0.7. Please also add the service load combinations of DL+SL, and DL+0.7*E, and 0.6*DL+0.7*E, and in the strength load combinations add 0.7*DL+E.

 

6. SPECIAL INSPECTOR LETTER

Please provide a letter from the Owner indicating who they will be hiring to provide special inspections for this project. The special inspector(s) must be licensed by MOA in the type(s) of inspection(s) to be provided.

 

Please provide a written response to the comments and include one copy of additional or revise calculations, and two copies of additional or revise drawings. While not required it is extremely helpful to the reviewer if the response indicates where in the submittal each comments has been addressed.

 

All submittals should be sent to the permit manager.