Comments for 3/29/13 submittal:
1.) Provide haul route for demolition, earthwork and proposed paving construction operations meeting the requirements of AMC 9.46.410; the shortest, most direct route, which minimizes travel on local and collector roadways shall be used.
2.) Please show the location of the stabilized construction access(es) to the site.
3.) Provide certified lighting analysis and glare statement for the proposed field lighting.
4.) This review shall be considered to be incomplete pending receipt and approval of the requested revisions or additional comments. 4/1/13 ~DF~