Reviewed by: Bergstrom, Leigh W. Permit #: C11-2221
Phone: 343-8326 Date: 9/14/2012
Fax: 249-7615
Email: BergstromLW@muni.org
Permit Manager: Jinny Day
Phone: 343-8338
Email: DayJR@muni.org
Project: GSE HANGAR/STORAGE BUILDING
Review Number: 303178
0) 8-30-12 FULL SIZE PLANS DATE STAMPED 05/09/12 WERE SUBMITTED ON AUGUST 13th WITH NO APPARENT REVISIONS OR RESPONSES TO THE FOLLOWING COMMENTS DATED 7-05-12. PROVIDE THREE SETS OF REVISED DRAWINGS AND A LETTER ADDRESSING ALL OF THE COMMENTS. RESOLVED 9-14-12. A FEW SMALL CHANGES WERE DETECTED ON THE ENLARGED PLAN SET.
1) STATUS: 7-05-12 Comments to be addressed. 8-02-12 FOOTING AND FOUNDATION ONLY APPROVED. COMMENTS TO BE ADDRESSED. 9-14-12 COMMENTS TO BE ADDRESSED.
2) The following comments based on the 2009 International Building, Mechanical and Fuel Gas Codes must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the IBC, IMC, IFGC or any federal, state or local regulations. RESOLVED 9-14-12.
3) The current plan set has many details that are not readable due to the reduced print size. Please provide three full size sets of drawings so that a complete review may be accomplished. Further comments may result after ledgible sets are provided. RESOLVED PER RESUBMITTAL RECEIVED 8-13-12.
4) Provide structural and seismic calculations plus fastening details for WWT-1 to include engineers stamp and signature, for structural review on a deferred submittal basis. RESOLVED 9-14-12.
5) Boiler #B1 is not permitted on the hangar floor (IBC 412.4.4). RESOLVED PER RESUBMITTAL RECEIVED 8-13-12.
6) Provide boiler piping details similar to the water heater details. RESOLVED PER RESUBMITTAL RECEIVED 8-13-12.
7) The high efficiency gas furnace GF-1 requires condensate to be processed through a condensate neutralizer (local amendment to IFGC307.2). 9-14-12 UNRESOLVED. THIS WAS NOT SHOWN ON THE PLANS.
8) Gas unit heaters installed in a Class III hangar are required to be a minimum of 10 feet vertically above the upper surface of the wings or engine enclosures of the tallest aircraft which may be housed within the hangar (local amendment to IFGC 305.11). Please clarify. 9-14-12 UNRESOLVED. 10 FEET AFF IS NOT ADEQUATE CLARIFICATION. RTH-1 THRU 3 SHOULD ALSO BE INCLUDED WITHIN THIS REQUIREMENT.
9) Provide radiant slab tubing performance data and details to include but not limited to maximum tubing length, GPM per loop, tubing size, zone header details, locations and areas served, insulation, tie downs, etc. 9-14-12 UNRESOLVED. TUBING LAYOUT TO MEET THE REQUIREMENTS OF M.O.A. POLICY #M.02. THIS MAY BE PROVIDED ON A DEFERRED SUBMITTAL BASIS ALONG WITH PERFORMANCE DATA; HOWEVER, MANIFOLD PIPING, UNDERLAYMENT AND TIEDOWN DETAILS ARE REQUIRED.
10) NEW 9-14-12 PROVIDE RTH LAYOUTS AND VENTING DETAILS.
11) NEW 9-14-12 RTH-1 THRU 3 ARE MISSING FROM THE EQUIPMENT SCHEDULE.
12) NEW 9-14-12 HEATING ZONES B1 THRU B3 ARE NOT PROVIDED ON THE PLAN VIEW.
10) When the above comments have been addressed please update the plans at the MOA Plans Review Office with three sets of revised mechanical pages to include clouded changes, engineers stamp and signature.