Approved 6/20/2012 - Per phone conversation with CRW Engineer addressed concerns - Tank is double wall protected -Dike area is not required but provided. Height of tank support is < 8 inches - 2 hr protection not required. reference to 2006 IFC on sheet G3 is typo error - Project meets 2009 code edition. Addressing location of fuel shutoff with electrical engineer will locate further from area as required.
.
Per phone call from Engineer the shut off is within requirements of NFPA for bulk storage/process transfer. (Not > 100ft away). Since this is not a fleet fueling station for fueling motor vehicle fuel tanks the 20 to 100ft distance in IFC 22 does not apply. Researched & accepted. 6/22/2012