1. Provide an operations and maintenance manual. RESOLVED SME 11-29-11.
2. Provide a dewatering plan. RESOLVED SME 8-30-11.
3. Prior to a final CO provide a storm drain as-built/inventory certified by a PE.
4. OK for F&F. Initial grading and shallow excavation allowed. No deep excavation other that test holes allowed until a dewatering plan is submitted and approved. sme 7-18-11.
5. Complete the dewatering request form in the AG 21 and attach your dewatering plan to it.
6. Ok for shell only.
7. OK for full permit. sme 11-29-11.