6/1/2001
Electrical Plan Review Status:
The electrical plans have been reveiwed and approved.
1. Please address the following comments for full approval. 5/6//2011
2. The following comments based on the 2008 National Electrical Code (NEC) must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the NEC or any federal, state or local regulations.
3. ELECTRICAL ENGINEERING DESIGN REQUIREMENT:Please provide 100% designed engineered drawing by a registered professional electrical engineer of the State of Alaska. Refer to the administrative Code AAC 104.8.1.
4. EQUIPMENT REQUIRES THIRD PARTY LISTING:Please be aware that all equipment will require and be checked for third party listing per NEC 110-3. Any new or existing equipment to be reused or relocated will be checked for listing by the electrical inspector. Any equipment found without a listing will be required to go through testing to gain approval. Inspector to field verify. NO RESPONSE REQUIRED.
5. EXISTING SERVICE LOAD CALCULATIONS:
Sheet E500 (Existing Service Entrance Load Calculations). Every existing panel has significant load added to it. The plans show no calculations for the feeder loads for the existing section of the building as required by NEC Section 220.87. Please address.
6. When the above comments have been addressed, please update the electrical plans at the MOA Plans Review Office with three (3) sets of revised electrical pages to include clouded changes, electrical engineers stamp and signature.