Structural revision for new tenant, shaft revision for new tenant / tb
3/3/11 issued partial permit for pile installation only (tina)
1) STATUS: 2-17-11 Comments to be addressed. 3-4-11 APPROVED.
2) The following comments based on the 2006 International Building, Mechanical and Fuel Gas Codes must be resolved before a permit is issued. The approval of plans and specifications does not permit the violation of any section of the IBC, IMC, IFGC or any federal, state or local regulations. RESOLVED 3-4-11.
3) 3/M.101 Note "X" on D.101 references removal of HVAC supply to the basement mail room. It is assumed that would be the 10" S/A which is being capped. Please clarify how the ventilation requirements for the mail room will be met. RESOLVED PER E-MAIL OF 2-18-11.
4) 4/M.101 Note #12 on A.101 references rerouting insulated piping along the south end of the tenant space to the skybridge. Provide clarifying notes on the mechanical plans. RESOLVED PER E-MAIL OF 2-18-11.