| Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
| Fire Sprinkler Bracing Final | 3/25/2026 | D.Meneses | 3/25/2026 11:58:00 AM | Approved | Completed | 891312 |
| Fire Sprinkler Final | 5/1/2026 | | | Cancel | Completed | 891313 |
| Fire Sprinkler Final | 5/5/2026 | D.Meneses | 5/5/2026 6:37:00 AM | CondAppr | Completed | 899993 |
| Fire Sprinkler Piping Air Test | 3/25/2026 | D.Meneses | 3/25/2026 11:54:00 AM | Approved | Completed | 891311 |
| Fire Sprinkler Rough-In | 3/25/2026 | D.Meneses | 3/25/2026 12:04:00 PM | Approved | Completed | 891316 |
| Fire Sprinkler System Operational Test | | | | | Schedule Inspection | 891315 |
| Sprinkler Hydrostatic Test | 4/2/2026 | D.Meneses | 4/2/2026 10:37:00 AM | Approved | Completed | 895431 |
| Sprinkler Hydrostatic Test | 3/25/2026 | D.Meneses | 3/25/2026 11:49:00 AM | Cancel | Completed | 891314 |