Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
Fire Sprinkler Bracing Final | | | | | Schedule Inspection | 824531 |
Fire Sprinkler Bracing Final | 9/19/2024 | D.Meneses | 9/19/2024 4:25:00 PM | Partial | Completed | 792574 |
Fire Sprinkler Final | | | | | Schedule Inspection | 792572 |
Fire Sprinkler Piping Air Test | 4/23/2025 | D.Meneses | 4/23/2025 12:41:00 PM | Approved | Completed | 792577 |
Fire Sprinkler Rough-In | 4/22/2025 | D.Meneses | 4/22/2025 11:31:00 AM | Approved | Completed | 824536 |
Fire Sprinkler Rough-In | 9/19/2024 | D.Meneses | 9/19/2024 4:28:00 PM | Partial | Completed | 792575 |
Fire Sprinkler System Operational Test | | | | | Schedule Inspection | 792576 |
Sprinkler Hydrostatic Test | 4/22/2025 | D.Meneses | 4/22/2025 11:28:00 AM | Approved | Completed | 824530 |
Sprinkler Hydrostatic Test | 9/19/2024 | D.Meneses | 9/19/2024 4:22:00 PM | Partial | Completed | 792573 |