| Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
| Fire Sprinkler Bracing Final | 7/7/2023 | B.Meinhardt | 7/7/2023 4:26:00 PM | Approved | Completed | 764855 |
| Fire Sprinkler Bracing Final | 6/20/2023 | D.Meneses | 6/20/2023 3:31:00 PM | Partial | Completed | 754158 |
| Fire Sprinkler Final | 8/17/2023 | D.Meneses | 8/17/2023 3:23:00 PM | Approved | Completed | 754154 |
| Fire Sprinkler Piping Air Test | 8/7/2023 | D.Meneses | 8/7/2023 6:37:00 AM | Approved | Completed | 754159 |
| Fire Sprinkler Rough-In | 6/20/2023 | D.Meneses | 6/20/2023 3:44:00 PM | Approved | Completed | 754157 |
| Fire Sprinkler System Operational Test | 8/17/2023 | D.Meneses | 8/17/2023 3:20:00 PM | Approved | Completed | 754156 |
| Sprinkler Hydrostatic Test | 8/2/2023 | D.Meneses | 8/2/2023 12:15:00 PM | Approved | Completed | 770882 |
| Sprinkler Hydrostatic Test | 7/7/2023 | B.Meinhardt | 7/7/2023 4:23:00 PM | Approved | Completed | 764857 |
| Sprinkler Hydrostatic Test | 6/20/2023 | D.Meneses | 6/20/2023 3:40:00 PM | Partial | Completed | 754155 |