Inspection Type | Scheduled | Assigned To | Completed Date | Result | Schedule Inspection | Inspection No. |
Fire Standpipe Bracing Final | 3/8/2023 | D.Meneses | 3/8/2023 6:30:00 AM | Approved | Completed | 680958 |
Fire Standpipe Final | 3/9/2023 | D.Meneses | 3/9/2023 7:26:00 AM | Approved | Completed | 751424 |
Fire Standpipe Final | 3/8/2023 | D.Meneses | 3/8/2023 6:58:00 AM | Correction | Completed | 680959 |
Fire Standpipe Piping Hydrostatic Test | 10/6/2022 | D.Meneses | 10/6/2022 12:39:00 PM | Approved | Completed | 720428 |
Fire Standpipe Piping Hydrostatic Test | 6/27/2022 | D.Meneses | 6/27/2022 11:02:00 AM | Partial | Completed | 680960 |
Fire Standpipe Rough-In Inspection | | | 3/9/2023 7:34:00 AM | Approved | Completed | 735897 |
Fire Standpipe Rough-In Inspection | 10/6/2022 | D.Meneses | 10/6/2022 12:44:00 PM | Partial | Completed | 720429 |
Fire Standpipe Rough-In Inspection | 6/27/2022 | D.Meneses | 6/27/2022 11:07:00 AM | Partial | Completed | 680961 |