Muni.org > Departments > Development Services> Permit Information & Inspection Request
Click Here To View Another Inspection


Inspection #: 920032
Inspection Type: Final Plumbing
Inspector: E.Wood
Result: Correction
Comment: See corrections. If possible to have the prints on site instead of pictures of the drawings, it would be easier to tell what the scope of work is.

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
9/21/2026TransferPlumbFinalCommentsSee Inspector CommentsBoth the east side bathroom, and the west side bathroom toilets.Per 402.2 of the 2018 UPC " Where a fixture comes into contact with the wall or floor, the joint between the fixture and the wall or floor shall be made water tight." Please caulk the base of both toilets.
9/21/2026TransferPlumbFinalCommentsSee Inspector CommentsBoth the east side and west bathroom water Code compliance. Per the NEC an appliance chord is not allowed above the dropped ceiling. Please consult an electrical inspector.
9/21/2026TransferPlumbFinalCommentsSee Inspector CommentsThe east side bathroom and the breakroom sink.There is no hot water. Probably because there is no vacuum relief valve.
9/21/2026TransferPlumbFinalCommentsSee Inspector CommentsThe cold water supply to the east side electric water heater. Code compliance. Per the 2018 UPC 608.7, A vacuum relief valve shall be installed when the water heater is installed above the fixtures it serves.
9/21/2026TransferPlumbFinalCommentsSee Inspector CommentsThe electric water heaters. Above the east side and west side bathrooms.Code compliance. Seismic restraint is required for the water heaters, per the 2018 UPC 507.5. Per the MOA amendment to this section only one strap is required. This has been a code for a few decades.