Inspection #: 914006
Inspection Type: Post Tension
Inspector: B.Gilgus
Result: Approved
Comment: Clearance inspection on level 1.5 columns @ G.0/5&6, F.0/4,5,&6, and E.0/4&5. Clearances were adequate per the General Structural Notes. Preclosure- Level 1-2 wall 6.0/B.2-E.9 Reinforcement was adequate per S10-01 and details on S30-01. Level 2, pour 2 reinforcement- I observed placement of reinforcement and strand. Any deficiencies observed throughout the day were corrected. By the end of the inspection corrections were made on my observed deficiencies and the concerns addressed in the engineers report. The reinforcement and strand placement conformed to S10-02A, PT-2.00-2.02, RFI #186 and RFI #178.1. Approved

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
       