Muni.org > Departments > Development Services> Permit Information & Inspection Request
Click Here To View Another Inspection


Inspection #: 906923
Inspection Type: Fire Sprinkler Rough-In
Inspector: N.Thomson
Result: Correction
Comment: 1am if available 4th floor corridor Requested by: Jason Ando 9073889295 jando@yukonfire.com

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
7/21/2026TransferFireSprinkRough2Correction(s) #2Correct the following item(s):4th floor corridor<ol><li><p>The seismic bracing on the fourth floor was not fully torqued. Tighten all bracing connections to the required torque and verify compliance upon reinspection</p></li><li><p>Water leakage was observed during the hydrostatic test. Repair all leaks and successfully complete the required hydrostatic test prior to final approval.</p></li><li><p>Electrical wiring is in contact with the sprinkler piping. Support or reroute the wiring to maintain separation from the sprinkler piping and prevent contact between dissimilar materials that could result in galvanic corrosion.</p></li></ol>
6/22/2026TransferFireSprnkRoughOtherFire Sprinkler Rough Partial ApprovalFire Sprinkler Rough Partial Approval.&nbsp; &nbsp;List area(s) approvedNorth Covered Area onlyAll okay to proceed.
6/11/2026TransferFireSprnkRoughOtherFire Sprinkler Rough Partial ApprovalFire Sprinkler Rough Partial Approval.&nbsp; &nbsp;List area(s) approved1st Floor Pool, Gym and bathroomsAll okay to proceed.
6/4/2026TransferFireSprnkRoughOtherFire Sprinkler Rough Partial ApprovalFire Sprinkler Rough Partial Approval.&nbsp; &nbsp;List area(s) approved1st floor main hall and public bathroomsOkay to proceed.
5/19/2026TransferFireSprnkRoughOtherFire Sprinkler Rough Partial ApprovalFire Sprinkler Rough Partial Approval.&nbsp; &nbsp;List area(s) approved1st floor rooms only1st floor rooms are okay to cover.
3/17/2026TransferFireSprinkRough10Correction(s) #6Correct the following item(s):2nd floor hallprovide and maintain required space between Duct and sprinkler piping.
3/17/2026TransferFireSprinkRough1Correction(s) #1Correct the following item(s):2nd floor hallProvide information for compatibility with CPVC piping.&nbsp;
3/17/2026TransferFireSprnkRoughOtherFire Sprinkler Rough Partial ApprovalFire Sprinkler Rough Partial Approval.&nbsp; &nbsp;List area(s) approved2nd floor onlyokay to cover rooms only, Hall has correction.
1/15/2026TransferFireSprinkRough11NotesNotes: ADVISORY - Main piping runs along the length of the corridor could be subject to significant thermal expansion. Adjust piping and branch line penetrations as necessary // PANILO