| 7/21/2026 | Transfer | FireSprinkRough2 | Correction(s) #2 | Correct the following item(s): | 4th floor corridor | <ol><li><p>The seismic bracing on the fourth floor was not fully torqued. Tighten all bracing connections to the required torque and verify compliance upon reinspection</p></li><li><p>Water leakage was observed during the hydrostatic test. Repair all leaks and successfully complete the required hydrostatic test prior to final approval.</p></li><li><p>Electrical wiring is in contact with the sprinkler piping. Support or reroute the wiring to maintain separation from the sprinkler piping and prevent contact between dissimilar materials that could result in galvanic corrosion.</p></li></ol> |
| 6/22/2026 | Transfer | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | North Covered Area only | All okay to proceed. |
| 6/11/2026 | Transfer | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 1st Floor Pool, Gym and bathrooms | All okay to proceed. |
| 6/4/2026 | Transfer | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 1st floor main hall and public bathrooms | Okay to proceed. |
| 5/19/2026 | Transfer | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 1st floor rooms only | 1st floor rooms are okay to cover. |
| 3/17/2026 | Transfer | FireSprinkRough10 | Correction(s) #6 | Correct the following item(s): | 2nd floor hall | provide and maintain required space between Duct and sprinkler piping. |
| 3/17/2026 | Transfer | FireSprinkRough1 | Correction(s) #1 | Correct the following item(s): | 2nd floor hall | Provide information for compatibility with CPVC piping. |
| 3/17/2026 | Transfer | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 2nd floor only | okay to cover rooms only, Hall has correction. |
| 1/15/2026 | Transfer | FireSprinkRough11 | Notes | Notes: | | ADVISORY - Main piping runs along the length of the corridor could be subject to significant thermal expansion. Adjust piping and branch line penetrations as necessary // PANILO |