| Date | Status | Code | Description | Ref | Location | Comments |
| 5/27/2026 | Transfer | Correct service item below | * | | Available fault current calculations. | Calculations are in a format that is not familiar. Some values at the same equipment seem to differ. Clarification of available fault currents at various points in the system is necessary. |
| 5/27/2026 | Transfer | Correct service item below | * | | Grounding electrode conductor to ufer. | Is there a #4 CU brought to the service? |
| 5/27/2026 | Transfer | Correct service item below | * | | Service grounding termination. | #6 CU for ground rods cannot terminate under the same lug as larger stranded conductor. |
| 5/26/2026 | Transfer | Correct service item below | * | | MDP. | Rigid 90s in bottom of switch gear require a bonding bushing and jumper sized per 250.122 for 3500A breaker. |
| 5/26/2026 | Transfer | Correct service item below | * | | Parallel feeder runs from service to main distribution panel. | 250.122(F)(1)(b) requires a full sized equipment grounding conductor in each parallel conduit run. Table 250.122 requires a 500KCMIL equipment ground for 3500A breaker. |