Date | Status | Code | Description | Ref | Location | Comments |
4/22/2025 | | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 1st floor only, except pool area | Okay to cover. |
2/5/2025 | | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 2nd floor only | All okay to proceed. |
1/17/2025 | | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | Penthouse & 1st floor boiler room | All okay to proceed |
10/22/2024 | | FireSprnkRoughOther | Fire Sprinkler Rough Partial Approval | Fire Sprinkler Rough Partial Approval. List area(s) approved | 3rd and 4th floor | All okay to proceed |