Inspection #: 841612
Inspection Type: Plumbing Rough
Inspector: J.Bean
Result: Correction
Comment: DWV Piping and Test Approved to include fixtures draining from second floor to tie in at the main. Note: Based on inspection and evaluation with installer grade can be achieved to gain elevation to tie into existing sewer main. Note: Once flex's installed on hydronic piping test must be performed before covering. See Corrections

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
3/13/2025TransferPlumbRgh14CommentsSee Inspectors CommentsExterior Hydronic PipingPer 2018 IMC Section 1202.7 Flexible connectors, expansion are required from one structure to another, one pad to another pad. Per IMC Section 12.06.9 Stresses and Strains - Piping to be installed so as to prevent strains and stresses on piping
3/13/2025TransferPlumbRgh14CommentsSee Inspectors CommentsBasement Sump Pit (floor sink)Per 2018 UPC 710.3 thru 710.10 Listed sewage ejectors required to serve any approved receptors or floor drain. (Listed sewage ejector must be water tight) Note: Floor sink must be trapped when connected to permanent sewer. Note: Based on inspection and evaluation with installer grade can be achieved to gain elevation to tie into existing sewer main. Note: A field change order form could delete installation for the open sump pump.
2/11/2025CorrectedPlumbRgh14CommentsSee Inspectors CommentsIndirect draining sinks & equipment1" air gap required to serve indirect draining sinks & equipment per 2018 UPC.
2/11/2025CorrectedPlumbRgh14CommentsSee Inspectors CommentsSteamer kettle, steam oven & espresso machineVented dual check ASSE 1012 required to serve all seam producing equipment per 2018 UPC & Cross Connection Control Manual.