Date | Status | Code | Description | Ref | Location | Comments |
9/20/2024 | Transfer | FireAlarmRough7 | Correction(s) #4 | <div>Correct the following item(s):</div><div><br></div> | | Notes only: Discussed the following: (1) P-link can be run as 2-2conductor cables and wiring shall have labels installed at terminations. (2) All wring termination in cabinets will have labels identification to what circuit it is. (3) Elevator device in the shaft and access to devices from outside the shaft. Email sent to show proper access to smoke detectors in the shaft. (4) Elevator pit detection and installing outside the pit test point (5) Getting the State permit 1B-special for all electricians that are installing the fire alarm and once everyone is licensed Electrical Administrator Coleman Barney would not have to be onsite at all times while the fire alarm system installation is on going. |
9/20/2024 | Transfer | FireAlarmRough6 | Correction(s) #3 | <div>Correct the following item(s):</div><div><br></div> | | Once correction items 1 and 2 are corrected, cover can be done on 4th floor, if all other MOA inspections are completed. |
9/20/2024 | Transfer | FireAlarmRough2 | Fire Alarm Rough-in Partial | Fire Alarm Rough-in Partial | | Partial Rough-in approved for the 4th floor.<div><br></div><div><br></div> |
9/20/2024 | Transfer | FireAlarmRough5 | Correction(s) #2 | <div>Correct the following item(s):</div><div><br></div> | | Verify that pull station will be 42 to 48 inches AFF measured to the activating handle or lever of the box |
9/20/2024 | Transfer | FireAlarmRough4 | Correction(s) #1 | <div>Correct the following item(s):</div><div><br></div> | | Wall mounted strobes boxes are mounted to low. Center of the lens of the strobe shall be between 80-96 inches AFF. Current mounting locations did not take in account the gypcrete flooring and finish floor level which will raise the floor up to 2 inches and the strobes being installed are at the bottom of the device. |