Inspection #: 804283
Inspection Type: Underground Plumbing
Inspector: Y.Dovba
Result: Partial
Comment: Underground dwv piping rough-in and tests Approved, including trap-primers. Restroom groups, floor drains, sinks and clean-outs, units 16, 18, 22 and 23 ok to cover. Units 18 and 21 100ft clean-out and 2-floor drains are approved for cover. NOTE: Per 2018 UPC amendment 314.4 use clean fill when back-filling and protect piping through slab. NOTE: Per 2018 UPC section 707.4 install clean-outs at upper terminals above slab on runs exceeding 5ft horizontal runs.