| Date | Status | Code | Description | Ref | Location | Comments |
| 4/10/2024 | Transfer | 01 | See inspection comments | | | Door controllers in stairwells incomplete. |
| 4/10/2024 | Transfer | 01 | See inspection comments | | | Boiler room incomplete. |
| 4/10/2024 | Corrected | 01 | See inspection comments | | | Safe off exposed wiring in stairwells and in rooms 319 and neighboring rooms. |
| 4/10/2024 | Corrected | 01 | See inspection comments | | | Exit sign required at 2nd floor exit. |
| 4/10/2024 | Corrected | 01 | See inspection comments | | | Work space required at 2nd floor inverter. |
| 4/10/2024 | Transfer | 01 | See inspection comments | | | If building is intended to be partially occupied before project completion a deferred submittal must be provided which details the Phase Plan. The Phase Plan must identify the portions of the building intended to be occupied, life safety systems, egress paths, access to electrical systems, and construction area separation methodology. |