| Date | Status | Code | Description | Ref | Location | Comments |
| 1/10/2024 | Transfer | Correct following Item | | | Circuits supplying battery back-up luminaires. | Could not verify proper circuitry. May need an early inspection to be able to turn off circuits. |
| 12/27/2023 | Transfer | Correct following Item | | | 4th floor | No power at emergency lights at grid 4D and 5B. |
| 12/27/2023 | Transfer | Correct following Item | | | Elevator lobby on 4th floor | Emergency lighting must be on local lighting circuit or on dedicated circuit in an area with no less than 3 lighting circuits. |
| 12/27/2023 | Transfer | Correct following Item | | | Throughout | All luminaires require 2 seismic wires installed on opposite corners. Additionally, either all 4 tabs must hook over and under the top edge of the grid or have the other 2 corners screwed to the grid. UPDATE TO THIS CORRECTION: 4TH AND 8TH FLOOR SPOT CHECK REVEALED NUMEROUS LIGHTS NOT SCREWED TO GRID AND WITHOUT (4) TABS ENGAGED WITH THE CEILING GRID. (1) FIXTURE WITH SEISMIC WIRES NOT ON OPPOSITE CORNERS. |